Progress Details Report

Madmalne Bhotad MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 24167000.0010178594.00
2 Hill side Cutting & Slip clearence in (KM) 2.832.83
3 R/Wall, B/ Wall Type Protection works in (m) 914.00850.00
4 G-2 in (KM) 4.600.00
5 G-3 in (KM) 3.250.00
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 3.250.00
7 Cause Way in (No) 3.000.00
8 Culverts/Scupper in (No) 5.003.00
9 longitudinal Drain in (m) 3200.002000.00
10 Crash Barrier in (m) 110.000.00
11 Parapet in (No) 140.000.00
12 Road Furniture in (No) 233.000.00
13 Other Allied Works & Finishing Work in (Job) 1.000.00
14 Quality in (%) 88.31