Progress Details Report

Baluwakot Paiya-Pori MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 56160000.0059328221.00
2 Hill side Cutting & Slip clearence in (KM) 7.507.50
3 R/Wall, B/ Wall Type Protection works in (m) 1436.001436.00
4 G-2 in (KM) 1.751.75
5 G-3 in (KM) 9.209.20
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 9.209.20
7 Cause Way in (No) 0.000.00
8 Culverts/Scupper in (No) 21.0021.00
9 longitudinal Drain in (m) 9300.009300.00
10 Crash Barrier in (m) 0.000.00
11 Parapet in (No) 332.00332.00
12 Road Furniture in (No) 390.00390.00
13 Other Allied Works & Finishing Work in (Job) 1.001.00
14 Quality in (%) 88.17