Progress Details Report

Badabe Seligya MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 34421000.0042354487.00
2 Hill side Cutting & Slip clearence in (KM) 9.500.00
3 R/Wall, B/ Wall Type Protection works in (m) 609.00609.00
4 GSB/RBI/G-1 in (KM) 9.509.50
5 G-2 in (KM) 19.0019.00
6 G-3 in (KM) 9.509.50
7 PC/CC i/c Prime Coat, Tack Coat in (KM) 9.509.50
8 Cause Way in (No) 3.003.00
9 Culverts/Scupper in (No) 32.0032.00
10 longitudinal Drain in (m) 9385.009385.00
11 Parapet in (No) 100.00100.00
12 Road Furniture in (No) 113.00113.00
13 Quality in (%) 85.07