Progress Details Report

Nainipatal Madmaley MR (Ch-7 to 13.162 Km)
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 22806000.0019607580.00
2 Hill side Cutting & Slip clearence in (KM) 1.861.86
3 R/Wall, B/ Wall Type Protection works in (m) 290.00290.00
4 G-2 in (KM) 1.001.00
5 G-3 in (KM) 1.251.25
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 6.166.16
7 Cause Way in (No) 3.003.00
8 Culverts/Scupper in (No) 7.007.00
9 longitudinal Drain in (m) 6126.006126.00
10 Parapet in (No) 500.00500.00
11 Road Furniture in (No) 489.00489.00
12 Other Allied Works & Finishing Work in (Job) 1.001.00
13 Quality in (%) 95