Progress Details Report

Shishu Mandir-Nanasen Motor Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 15383000.0016918553.25
2 R/Wall, B/ Wall Type Protection works in (m) 214.00214.00
3 G-3 in (KM) 1.251.25
4 PC/CC i/c Prime Coat, Tack Coat in (KM) 2.752.75
5 Cause Way in (No) 1.001.00
6 longitudinal Drain in (m) 2215.002215.00
7 Parapet in (No) 250.00250.00
8 Road Furniture in (No) 39.0039.00
9 Other Allied Works & Finishing Work in (Job) 1.001.00
10 Quality in (%) 86.71