Progress Details Report

Madanpur Nani motor road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 92862000.0095185168.00
2 Hill side Cutting & Slip clearence in (KM) 10.1210.12
3 R/Wall, B/ Wall Type Protection works in (m) 2567.002567.00
4 G-3 in (KM) 10.1210.12
5 PC/CC i/c Prime Coat, Tack Coat in (KM) 10.1210.12
6 Cause Way in (No) 5.005.00
7 longitudinal Drain in (m) 9271.009271.00
8 Crash Barrier in (m) 0.000.00
9 Parapet in (No) 430.00430.00
10 Road Furniture in (No) 955.00955.00
11 Quality in (%) 87.23