Charma Jaurasi Lakhatigaon
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 114682000.0027668819.00
2 Hill side Cutting & Slip clearence in (KM) 18.8516.00
3 R/Wall, B/ Wall Type Protection works in (m) 2000.001706.00
4 G-2 in (KM) 7.230.00
5 G-3 in (KM) 7.480.00
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 18.850.00
7 Cause Way in (No) 9.003.00
8 Culverts/Scupper in (No) 65.0048.00
9 longitudinal Drain in (m) 18425.001425.00
10 Crash Barrier in (m) 195.000.00
11 Parapet in (No) 1238.000.00
12 Road Furniture in (No) 1082.000.00
13 Other Allied Works & Finishing Work in (Job) 4.000.00
14 Quality in (%) 90.00