Progress Details Report

Pahargaon Bandur MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 26807000.0026806767.00
2 Hill side Cutting & Slip clearence in (KM) 1.531.53
3 R/Wall, B/ Wall Type Protection works in (m) 1638.001638.00
4 G-2 in (KM) 6.006.00
5 G-3 in (KM) 6.006.00
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 6.006.00
7 longitudinal Drain in (m) 5790.005790.00
8 Parapet in (No) 382.00382.00
9 Road Furniture in (No) 76.0076.00
10 Quality in (%) 87.63