Progress Details Report

Kasyali Khobra MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 47179000.0039067612.23
2 Hill side Cutting & Slip clearence in (KM) 1.761.76
3 R/Wall, B/ Wall Type Protection works in (m) 950.00950.00
4 GSB/RBI/G-1 in (KM) 7.037.03
5 G-2 in (KM) 7.667.66
6 G-3 in (KM) 7.637.63
7 PC/CC i/c Prime Coat, Tack Coat in (KM) 7.637.63
8 Cause Way in (No) 2.002.00
9 Culverts/Scupper in (No) 20.0020.00
10 longitudinal Drain in (m) 4970.004970.00
11 Parapet in (No) 72.0072.00
12 Road Furniture in (No) 107.00107.00
13 Other Allied Works & Finishing Work in (Job) 1.001.00
14 Quality in (%) 86.63