Progress Details Report

Nathukhal Pokhrikhet MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 17411000.0023276496.17
2 Hill side Cutting & Slip clearence in (KM) 2.662.66
3 GSB/RBI/G-1 in (KM) 0.300.30
4 G-2 in (KM) 0.300.30
5 G-3 in (KM) 3.203.20
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 7.007.00
7 Cause Way in (No) 0.000.00
8 Culverts/Scupper in (No) 20.0020.00
9 longitudinal Drain in (m) 6080.006080.00
10 Parapet in (No) 71.0071.00
11 Other Allied Works & Finishing Work in (Job) 1.001.00
12 Quality in (%) 90