Progress Details Report

Birsanikhal-Kota-Silsu-bhutnisi MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 15124000.0019300254.00
2 Hill side Cutting & Slip clearence in (KM) 0.500.50
3 R/Wall, B/ Wall Type Protection works in (m) 280.00280.00
4 GSB/RBI/G-1 in (KM) 0.000.00
5 G-2 in (KM) 0.000.00
6 G-3 in (KM) 0.000.00
7 PC/CC i/c Prime Coat, Tack Coat in (KM) 0.000.00
8 Cause Way in (No) 11.000.00
9 Culverts/Scupper in (No) 2.002.00
10 longitudinal Drain in (m) 3300.003300.00
11 Crash Barrier in (m) 150.000.00
12 Road Furniture in (No) 2.002.00
13 Env. Man & Moni Plan in (Job) 1.000.00
14 Other Allied Works & Finishing Work in (Job) 1.001.00
15 Quality in (%) 87.09