Progress Details Report

Rikhanikhal- chanikhal Motor Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 13260000.0023313950.00
2 Hill side Cutting & Slip clearence in (KM) 0.620.62
3 R/Wall, B/ Wall Type Protection works in (m) 103.00103.00
4 G-2 in (KM) 0.900.90
5 G-3 in (KM) 2.402.40
6 Culverts/Scupper in (No) 3.003.00
7 longitudinal Drain in (m) 9600.009600.00
8 Crash Barrier in (m) 150.00150.00
9 Parapet in (No) 230.00230.00
10 Road Furniture in (No) 53.0053.00
11 Other Allied Works & Finishing Work in (Job) 1.001.00
12 Quality in (%) 85.84