Progress Details Report

Pokhal-Bhawansi-mandlu motor road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 86810000.0087062235.06
2 Hill side Cutting & Slip clearence in (KM) 8.548.54
3 R/Wall, B/ Wall Type Protection works in (m) 1143.001143.00
4 GSB/RBI/G-1 in (KM) 8.008.00
5 G-2 in (KM) 8.008.00
6 G-3 in (KM) 12.0012.00
7 Cause Way in (No) 9.009.00
8 Culverts/Scupper in (No) 22.0022.00
9 longitudinal Drain in (m) 17330.0017330.00
10 Crash Barrier in (m) 612.00612.00
11 Parapet in (No) 380.00380.00
12 Road Furniture in (No) 148.00148.00
13 Other Allied Works & Finishing Work in (Job) 1.001.00
14 Quality in (%) 89.71