Progress Details Report

Pauri-maroda-bayasghat-devprayag MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 84201000.0084271512.00
2 Hill side Cutting & Slip clearence in (KM) 3.383.38
3 R/Wall, B/ Wall Type Protection works in (m) 1210.001210.00
4 G-3 in (KM) 1.221.22
5 BM i/c Prime Coat, Tack Coat in (KM) 22.0022.00
6 SDBC i/c Tackcoat in (KM) 22.0022.00
7 Cause Way in (No) 2.002.00
8 Culverts/Scupper in (No) 17.0017.00
9 Crash Barrier in (m) 596.00596.00
10 Parapet in (No) 280.00280.00
11 Env. Man & Moni Plan in (Job) 0.000.00
12 Other Allied Works & Finishing Work in (Job) 1.001.00
13 Quality in (%) 89.68