Progress Details Report

Padampuri Harakhan Kathgodam Motor Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 159950000.00159725487.00
2 Hill side Cutting & Slip clearence in (KM) 0.200.20
3 R/Wall, B/ Wall Type Protection works in (m) 7620.007620.00
4 GSB/RBI/G-1 in (KM) 0.150.15
5 G-2 in (KM) 1.801.80
6 BM i/c Prime Coat, Tack Coat in (KM) 6.806.80
7 SDBC i/c Tackcoat in (KM) 27.5027.50
8 Culverts/Scupper in (No) 17.0017.00
9 longitudinal Drain in (m) 26500.0026500.00
10 Crash Barrier in (m) 4000.004000.00
11 Parapet in (No) 3000.003000.00
12 Road Furniture in (No) 272.00272.00
13 Other Allied Works & Finishing Work in (Job) 5.005.00
14 Quality in (%) 88.83