Ranghadwala to Nagal road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 3699000.001986088.10
2 Hill side Cutting & Slip clearence in (KM) 1.601.60
3 GSB/RBI/G-1 in (KM) 0.190.19
4 G-2 in (KM) 0.180.18
5 G-3 in (KM) 0.180.18
6 Culverts/Scupper in (No) 1.000.00
7 Road Furniture in (No) 1.001.00
8 Quality in (%) 90