Progress Details Report

GT road to Lavva road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 2259000.001378128.50
2 Hill side Cutting & Slip clearence in (KM) 1.401.40
3 PC/CC i/c Prime Coat, Tack Coat in (KM) 1.401.40
4 Culverts/Scupper in (No) 1.000.00
5 Road Furniture in (No) 4.004.00
6 Quality in (%) 90