Progress Details Report

Suryadhar Sangaoun Motor Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 10230000.0018167467.35
2 R/Wall, B/ Wall Type Protection works in (m) 416.70416.70
3 GSB/RBI/G-1 in (KM) 1.431.43
4 Culverts/Scupper in (No) 9.009.00
5 longitudinal Drain in (m) 0.000.00
6 Crash Barrier in (m) 0.000.00
7 Quality in (%) 90