Progress Details Report

Koruba Kwarana Mangrauli MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 53467000.0052683555.00
2 Hill side Cutting & Slip clearence in (KM) 7.007.00
3 R/Wall, B/ Wall Type Protection works in (m) 1036.001036.00
4 GSB/RBI/G-1 in (KM) 7.007.00
5 G-2 in (KM) 7.007.00
6 G-3 in (KM) 7.007.00
7 PC/CC i/c Prime Coat, Tack Coat in (KM) 7.007.00
8 BM i/c Prime Coat, Tack Coat in (KM) 7.000.25
9 Culverts/Scupper in (No) 15.0015.00
10 longitudinal Drain in (m) 7000.007000.00
11 Crash Barrier in (m) 345.00345.00
12 Road Furniture in (No) 35.0035.00
13 Quality in (%) 89.94