Progress Details Report

Punav-Sipty Nayari Motor Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 39536000.0039229899.00
2 Hill side Cutting & Slip clearence in (KM) 0.290.29
3 R/Wall, B/ Wall Type Protection works in (m) 1843.001843.00
4 G-2 in (KM) 5.405.40
5 G-3 in (KM) 5.405.40
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 5.405.40
7 Cause Way in (No) 1.001.00
8 Culverts/Scupper in (No) 16.0016.00
9 longitudinal Drain in (m) 5250.005250.00
10 Crash Barrier in (m) 404.00404.00
11 Parapet in (No) 260.00260.00
12 Road Furniture in (No) 101.00101.00
13 Other Allied Works & Finishing Work in (Job) 1.001.00
14 Quality in (%) 90.14