Progress Details Report

Laiuwapani-Banlekh Motor Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 35524000.0035506651.00
2 R/Wall, B/ Wall Type Protection works in (m) 1700.001700.00
3 G-2 in (KM) 1.961.96
4 G-3 in (KM) 3.403.40
5 PC/CC i/c Prime Coat, Tack Coat in (KM) 8.408.40
6 Cause Way in (No) 6.006.00
7 Culverts/Scupper in (No) 49.0049.00
8 longitudinal Drain in (m) 8000.008000.00
9 Crash Barrier in (m) 161.30161.30
10 Parapet in (No) 365.00365.00
11 Road Furniture in (No) 124.00124.00
12 Other Allied Works & Finishing Work in (Job) 1.001.00
13 Quality in (%) 92.23