Progress Details Report

Kanakchouri- Pokhta -Rauta motor road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 16262000.0021029620.60
2 Hill side Cutting & Slip clearence in (KM) 2.222.22
3 R/Wall, B/ Wall Type Protection works in (m) 517.00517.00
4 G-3 in (KM) 2.222.22
5 PC/CC i/c Prime Coat, Tack Coat in (KM) 2.222.22
6 Culverts/Scupper in (No) 8.008.00
7 longitudinal Drain in (m) 2220.002220.00
8 Parapet in (No) 80.0080.00
9 Road Furniture in (No) 28.0028.00
10 Quality in (%) 90