Progress Details Report

Sarmola Motor Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 7072000.006821933.01
2 R/Wall, B/ Wall Type Protection works in (m) 385.00385.00
3 GSB/RBI/G-1 in (KM) 1.401.40
4 G-2 in (KM) 1.401.40
5 G-3 in (KM) 1.401.40
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 1.401.40
7 Culverts/Scupper in (No) 4.004.00
8 longitudinal Drain in (m) 1400.001400.00
9 Parapet in (No) 110.00110.00
10 Road Furniture in (No) 24.0024.00
11 Quality in (%) 89.49