Progress Details Report

Semi Bend to Siwai Motor Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 19601000.0024421207.18
2 Hill side Cutting & Slip clearence in (KM) 3.003.00
3 GSB/RBI/G-1 in (KM) 3.003.00
4 G-2 in (KM) 3.003.00
5 PC/CC i/c Prime Coat, Tack Coat in (KM) 3.003.00
6 Cause Way in (No) 5.005.00
7 Culverts/Scupper in (No) 10.0010.00
8 longitudinal Drain in (m) 2815.002815.00
9 Crash Barrier in (m) 80.0080.00
10 Road Furniture in (No) 35.0035.00
11 Quality in (%) 88.78