Progress Details Report

Nagnath Link MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 12129000.0010140661.91
2 Hill side Cutting & Slip clearence in (KM) 1.651.65
3 G-2 in (KM) 1.651.65
4 PC/CC i/c Prime Coat, Tack Coat in (KM) 1.651.65
5 longitudinal Drain in (m) 1650.001650.00
6 Parapet in (No) 40.0040.00
7 Road Furniture in (No) 70.0070.00
8 Quality in (%) 90.49