Progress Details Report

Jaurasi - Hapla - Dhotidhar MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 13865000.0011317466.00
2 Hill side Cutting & Slip clearence in (KM) 1.701.70
3 R/Wall, B/ Wall Type Protection works in (m) 410.00410.00
4 G-2 in (KM) 1.301.30
5 G-3 in (KM) 1.701.70
6 Cause Way in (No) 7.007.00
7 Culverts/Scupper in (No) 0.000.00
8 longitudinal Drain in (m) 1700.001700.00
9 Parapet in (No) 70.0070.00
10 Road Furniture in (No) 83.0083.00
11 Quality in (%) 89.34