Progress Details Report

Okadi Ana Lohar Chada Gairlekh MR Phase2 (Ch-6 to 12 Km)
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 52573000.0034619624.00
2 Hill side Cutting & Slip clearence in (KM) 0.990.99
3 R/Wall, B/ Wall Type Protection works in (m) 631.00631.00
4 G-2 in (KM) 5.905.90
5 G-3 in (KM) 5.905.90
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 5.901.30
7 Cause Way in (No) 2.002.00
8 Culverts/Scupper in (No) 26.0026.00
9 longitudinal Drain in (m) 5.905.50
10 Crash Barrier in (m) 908.00908.00
11 Parapet in (No) 468.00468.00
12 Road Furniture in (No) 385.002.00
13 Env. Man & Moni Plan in (Job) 1.000.00
14 Quality in (%) 88.28