Progress Details Report

Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km)
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 95324000.0094738943.00
2 Hill side Cutting & Slip clearence in (KM) 9.939.93
3 G-2 in (KM) 3.103.10
4 G-3 in (KM) 3.103.10
5 PC/CC i/c Prime Coat, Tack Coat in (KM) 15.4615.46
6 Cause Way in (No) 25.0025.00
7 Culverts/Scupper in (No) 30.0030.00
8 longitudinal Drain in (m) 15455.0015455.00
9 Crash Barrier in (m) 2460.002460.00
10 Parapet in (No) 1700.001700.00
11 Road Furniture in (No) 613.00613.00
12 Env. Man & Moni Plan in (Job) 1.001.00
13 Other Allied Works & Finishing Work in (Job) 1.001.00
14 Quality in (%) 90.79