Progress Details Report

Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km)
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 87931000.0021670576.00
2 Hill side Cutting & Slip clearence in (KM) 9.937.75
3 R/Wall, B/ Wall Type Protection works in (m) 219.00219.00
4 G-2 in (KM) 3.101.50
5 G-3 in (KM) 3.100.05
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 15.460.00
7 Cause Way in (No) 18.004.50
8 Culverts/Scupper in (No) 38.0024.00
9 longitudinal Drain in (m) 15455.003500.00
10 Crash Barrier in (m) 1160.000.00
11 Parapet in (No) 780.000.00
12 Road Furniture in (No) 613.001.00
13 Env. Man & Moni Plan in (Job) 1.000.00
14 Other Allied Works & Finishing Work in (Job) 1.000.00
15 Quality in (%) 87.10