Progress Details Report

Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km)
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 96866000.0038246401.00
2 Hill side Cutting & Slip clearence in (KM) 9.938.13
3 R/Wall, B/ Wall Type Protection works in (m) 442.00239.00
4 G-2 in (KM) 3.102.60
5 G-3 in (KM) 3.100.05
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 15.465.50
7 Cause Way in (No) 18.005.00
8 Culverts/Scupper in (No) 38.0027.00
9 longitudinal Drain in (m) 15455.005000.00
10 Crash Barrier in (m) 1160.000.00
11 Parapet in (No) 1120.00430.00
12 Road Furniture in (No) 613.001.00
13 Env. Man & Moni Plan in (Job) 1.001.00
14 Other Allied Works & Finishing Work in (Job) 1.001.00
15 Quality in (%) 89.62