Progress Details Report

Kapkot- Tehsil-Poling MR Phase2
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 39413000.0044724624.00
2 Hill side Cutting & Slip clearence in (KM) 1.111.11
3 GSB/RBI/G-1 in (KM) 3.253.25
4 G-2 in (KM) 2.452.45
5 G-3 in (KM) 2.452.45
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 3.253.25
7 Cause Way in (No) 3.003.00
8 Culverts/Scupper in (No) 13.0013.00
9 Crash Barrier in (m) 273.00273.00
10 Parapet in (No) 65.0065.00
11 Road Furniture in (No) 182.00182.00
12 Other Allied Works & Finishing Work in (Job) 2.502.50
13 Quality in (%) 85.74