Progress Details Report

Dyuni Sukanda MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 34098000.0045188296.00
2 Hill side Cutting & Slip clearence in (KM) 1.251.25
3 R/Wall, B/ Wall Type Protection works in (m) 1377.001377.00
4 GSB/RBI/G-1 in (KM) 2.362.36
5 G-2 in (KM) 2.442.44
6 G-3 in (KM) 4.804.80
7 Cause Way in (No) 5.005.00
8 Culverts/Scupper in (No) 7.007.00
9 longitudinal Drain in (m) 4700.004700.00
10 Crash Barrier in (m) 800.00800.00
11 Road Furniture in (No) 450.00450.00
12 Quality in (%) 86.97