Progress Details Report

Kandhar Reetha Talla Parkoti Sirkot Patharkhani MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 44299000.0034048222.00
2 Hill side Cutting & Slip clearence in (KM) 1.161.16
3 R/Wall, B/ Wall Type Protection works in (m) 910.00910.00
4 GSB/RBI/G-1 in (KM) 4.914.91
5 PC/CC i/c Prime Coat, Tack Coat in (KM) 4.914.91
6 Culverts/Scupper in (No) 11.0011.00
7 longitudinal Drain in (m) 4754.004754.00
8 Parapet in (No) 400.00400.00
9 Road Furniture in (No) 111.00111.00
10 Other Allied Works & Finishing Work in (Job) 2.002.00
11 Quality in (%) 88.22