Progress Details Report

Chaufala Mate Tilsari MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 43949000.0055629884.00
2 Hill side Cutting & Slip clearence in (KM) 0.850.85
3 GSB/RBI/G-1 in (KM) 6.006.00
4 G-3 in (KM) 6.006.00
5 Cause Way in (No) 2.002.00
6 Culverts/Scupper in (No) 24.0024.00
7 Crash Barrier in (m) 650.00650.00
8 Parapet in (No) 20.0020.00
9 Road Furniture in (No) 196.00196.00
10 Quality in (%) 84.93