Menu

Progress Details Report

Chaufala Mate Tilsari MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 43949000.0032827034.00
2 Hill side Cutting & Slip clearence in (KM) 0.970.85
3 R/Wall, B/ Wall Type Protection works in (m) 769.00769.00
4 GSB/RBI/G-1 in (KM) 6.006.00
5 G-3 in (KM) 6.005.35
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 6.001.80
7 Cause Way in (No) 1.000.00
8 Culverts/Scupper in (No) 24.0024.00
9 longitudinal Drain in (m) 5805.003700.00
10 Crash Barrier in (m) 350.000.00
11 Parapet in (No) 120.000.00
12 Road Furniture in (No) 113.001.00
13 Other Allied Works & Finishing Work in (Job) 1.000.00
14 Quality in (%) 88.36