Progress Details Report

Kanda-Saniudiay-Rawatsera MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 110850000.00111017188.38
2 Hill side Cutting & Slip clearence in (KM) 3.003.00
3 G-3 in (KM) 2.882.88
4 BM i/c Prime Coat, Tack Coat in (KM) 20.0020.00
5 SDBC i/c Tackcoat in (KM) 20.0020.00
6 Cause Way in (No) 4.004.00
7 Culverts/Scupper in (No) 22.0022.00
8 longitudinal Drain in (m) 16000.0016000.00
9 Crash Barrier in (m) 4006.004006.00
10 Parapet in (No) 99.0099.00
11 Quality in (%) 89.34