Progress Details Report

Dyangar-Kathyatbara-Aare bypass MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 57649000.0058200421.00
2 Hill side Cutting & Slip clearence in (KM) 1.021.02
3 GSB/RBI/G-1 in (KM) 1.161.16
4 G-2 in (KM) 5.255.25
5 G-3 in (KM) 5.255.25
6 BM i/c Prime Coat, Tack Coat in (KM) 5.105.10
7 SDBC i/c Tackcoat in (KM) 5.135.13
8 Culverts/Scupper in (No) 10.0010.00
9 longitudinal Drain in (m) 5210.005210.00
10 Crash Barrier in (m) 1000.001000.00
11 Road Furniture in (No) 192.00192.00
12 Other Allied Works & Finishing Work in (Job) 5.005.00
13 Quality in (%) 84.26