UDRP/PWD/02/36/RD/088
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
99 |
Package Name: |
UDRP/PWD/02/36/RD/088 |
Sanction Cost: |
1083.32 lakhs |
District: |
Chamoli |
Block: |
Ghat |
Constituency: |
Tharali |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 1268 Sema Bairaun Motor Road (10.500 KM.) (completed) |
|
Procurement: |
Package No.: 99
Package Name: UDRP/PWD/02/36/RD/088
Tender Date: 18-03-2015
Current Status: Agreement signed
Achieved on Date: 05-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/36/RD/088
Contractor Name: Laxman Singh Rawat
|
Start Date: 12-06-2015
Intended Completion Date: 08-07-2017
Original End Date: 11-09-2016
|
Total Bond Cost: 76257187.1 (762.57 lakhs)
Variation Cost: 24361004.14 (243.61 lakhs) Hence Total Bond Cost is 100618191.24 (1006.18 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2707159 for 71 days
LD Analysis for Milestone2: calculated LD is Rs 2097095 for 55 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 10.00 KM | 48.11 | 10.00 KM | 10.00 KM | 5.64 | 48.11 | 2. | R/Wall, B/ Wall Type Protection works | 4885.00 m | 288.21 | 4885.00 m | 4885.00 m | 33.8 | 288.21 | 3. | G-2 | 10.50 KM | 113.75 | 10.50 KM | 10.50 KM | 13.34 | 113.75 | 4. | G-3 | 10.50 KM | 82.60 | 10.50 KM | 10.50 KM | 9.69 | 82.60 | 5. | PC/CC i/c Prime Coat, Tack Coat | 10.50 KM | 138.60 | 10.50 KM | 10.50 KM | 16.25 | 138.60 | 6. | Cause Way | 7.00 No | 15.19 | 7.00 No | 7.00 No | 1.78 | 15.19 | 7. | Culverts/Scupper | 45.00 No | 91.34 | 45.00 No | 45.00 No | 10.71 | 91.34 | 8. | longitudinal Drain | 10500.00 m | 60.91 | 10500.00 m | 10500.00 m | 7.14 | 60.91 | 9. | Parapet | 250.00 No | 11.46 | 250.00 No | 250.00 No | 1.34 | 11.46 | 10. | Road Furniture | 239.00 No | 2.63 | 239.00 No | 239.00 No | 0.31 | 2.63 |
Total Amount: |
852.8 |
|
100 |
852.8 |
|
Remarks:
No Remarks
Work Program Made On:
13-07-2015
Updation of work program on:
22-01-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2015 | 66.13 lakhs |
2. | 30-November-2015 | 16.76 lakhs |
3. | 24-December-2015 | 24.99 lakhs |
4. | 25-January-2016 | 50.37 lakhs |
5. | 29-February-2016 | 55.81 lakhs |
6. | 30-March-2016 | 85.55 lakhs |
7. | 02-May-2016 | 27.87 lakhs |
8. | 31-May-2016 | 32.11 lakhs |
9. | 30-June-2016 | 109.21 lakhs |
10. | 31-August-2016 | 32.02 lakhs |
11. | 26-October-2016 | 36.06 lakhs |
12. | 17-December-2016 | 16.59 lakhs |
13. | 07-March-2017 | 57.15 lakhs |
14. | 31-March-2017 | 70.67 lakhs |
15. | 05-May-2017 | 35.24 lakhs |
16. | 20-May-2017 | 46.42 lakhs |
17. | 14-July-2017 | 79.14 lakhs |
18. | 28-July-2017 | 25.64 lakhs |
19. | 12-October-2017 | 48.71 lakhs |
20. | 27-November-2017 | 59.59 lakhs |
21. | 11-December-2017 | 26.62 lakhs |
22. | 28-August-2018 | 3.20 lakhs |
Total |
1005.85 lakhs |
% Payment |
99.97 % |
|
Advance Amount: 222.85 lakhs
Recovered Amount: 222.85 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 69 |
Number of Notice(s) issued: 75 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-03-2017 | Ch 1.750 | Social compliance | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
2. | 28-03-2017 | Ch 2.925 | Sprinkling of water over G3 | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
3. | 28-03-2017 | Ch 6.475 | Gradation of G3 | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
4. | 28-03-2017 | Ch 1.780 | Checking of coarse sand for type B seal coat | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
5. | 25-03-2017 | Ch 1.150 | Grievance by mota villagers for construction of scupper | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
6. | 25-03-2017 | Checking superelevation at ch 0.225 | Checking superelevation | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
7. | 25-03-2017 | Ch 0.150 | Gradation of G2 layer | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
8. | 08-03-2017 | Ch-10.500 | Site visit chief Sir | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
9. | 07-02-2017 | Ch 3.525 | Aiv test | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
10. | 07-02-2017 | Ch 10.300 | G2 layer thickness checking | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
11. | 07-02-2017 | Ch 1.800 | Slope checking of wall | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
12. | 07-02-2017 | Ch 1.125 | Thickness checking of drain | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
13. | 06-02-2017 | Ch-1.125 | C type drain work | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
14. | 02-02-2017 | Ch-3.100 | Slumptest ofcementconcrete inRaft | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
15. | 02-02-2017 | Ch-3.100 | 3M spanculvert RR Masonry | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
16. | 02-02-2017 | Ch-3.100 | 3M spanculvert span checking | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
17. | 02-02-2017 | Ch-6.900 | RR.DRYworkin R/w | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
18. | 01-02-2017 | Ch-2.600 | AIV testing G3 | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
19. | 13-12-2016 | Ch-5.850 | Causeway kharanja | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
20. | 18-11-2016 | 4.800 | Mowaja prakran | Piyush Mishra | JE | UDRP R&B Gopeshwar | See Pic |
|
|