UDRP/PWD/02/36/RD/083
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
94 |
Package Name: |
UDRP/PWD/02/36/RD/083 |
Sanction Cost: |
622.60 lakhs |
District: |
Chamoli |
Block: |
Karnaprayag |
Constituency: |
Karanprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 1225 Bagoli Koti Motor Road (11.200 KM.) (completed) |
|
Procurement: |
Package No.: 94
Package Name: UDRP/PWD/02/36/RD/083
Tender Date: 18-02-2015
Current Status: Agreement signed
Achieved on Date: 04-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/36/RD/083
Contractor Name: Universal Associates
|
Start Date: 11-06-2015
Intended Completion Date: 08-11-2016
Original End Date: 10-09-2016
|
Total Bond Cost: 55011028.02 (550.11 lakhs)
Variation Cost: 7233682.16 (72.34 lakhs) Hence Total Bond Cost is 62244710.18 (622.45 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 11.20 KM | 31.47 | 11.20 KM | 11.20 KM | 6.92 | 31.47 | 2. | R/Wall, B/ Wall Type Protection works | 2575.00 m | 120.08 | 2575.00 m | 2575.00 m | 26.4 | 120.08 | 3. | G-2 | 0.30 KM | 3.21 | 0.30 KM | 0.30 KM | 0.71 | 3.21 | 4. | G-3 | 2.45 KM | 18.23 | 2.45 KM | 2.45 KM | 4.01 | 18.23 | 5. | PC/CC i/c Prime Coat, Tack Coat | 11.20 KM | 124.10 | 11.20 KM | 11.20 KM | 27.29 | 124.10 | 6. | Cause Way | 7.00 No | 21.50 | 7.00 No | 7.00 No | 4.73 | 21.50 | 7. | Culverts/Scupper | 32.00 No | 72.04 | 32.00 No | 32.00 No | 15.84 | 72.04 | 8. | longitudinal Drain | 10510.00 m | 48.22 | 10510.00 m | 10510.00 m | 10.6 | 48.22 | 9. | Crash Barrier | 0.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 10. | Parapet | 500.00 No | 13.27 | 500.00 No | 500.00 No | 2.92 | 13.27 | 11. | Road Furniture | 249.00 No | 2.66 | 249.00 No | 249.00 No | 0.58 | 2.66 |
Total Amount: |
454.78 |
|
100 |
454.78 |
|
Remarks:
No Remarks
Work Program Made On:
13-07-2015
Updation of work program on:
06-06-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 24-September-2015 | 52.71 lakhs |
2. | 30-October-2015 | 75.34 lakhs |
3. | 30-January-2016 | 86.93 lakhs |
4. | 29-February-2016 | 45.02 lakhs |
5. | 28-March-2016 | 26.84 lakhs |
6. | 02-May-2016 | 82.83 lakhs |
7. | 29-June-2016 | 24.53 lakhs |
8. | 30-June-2016 | 51.44 lakhs |
9. | 31-August-2016 | 27.27 lakhs |
10. | 18-October-2016 | 44.48 lakhs |
11. | 26-October-2016 | 56.84 lakhs |
12. | 31-March-2017 | 48.20 lakhs |
Total |
622.43 lakhs |
% Payment |
100 % |
|
Advance Amount: 132.83 lakhs
Recovered Amount: 132.83 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 289 |
Number of Notice(s) issued: 74 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 30-01-2017 | Ch 8.585 | Measurement checking by EE sir | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
2. | 27-01-2017 | Ch 9.900 | Sign board | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
3. | 12-01-2017 | 0.015 | Scupper abutment work in progress | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
4. | 12-01-2017 | 0.015 | Rejected scupper abutment | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
5. | 30-11-2016 | 6.025 | Delinator and edge stone fixed | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
6. | 25-11-2016 | Ch 0.100 | Path way for movement of villagers connection road to griddle path | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
7. | 25-11-2016 | Ch 7.330 | Patch work | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
8. | 17-11-2016 | 4+420 | Painting on parapet | Mukesh Kumar Yadav | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
9. | 17-11-2016 | 0+100 | Parapet white wash complete | Mukesh Kumar Yadav | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
10. | 16-11-2016 | 3+825 | Extension joint seeling of causeway | Ajay Narayan Pandey | RE | DSC1 R&B WB Chamoli | See Pic |
11. | 16-11-2016 | 0+119 | Parapete penting. | Ajay Narayan Pandey | RE | DSC1 R&B WB Chamoli | See Pic |
12. | 27-10-2016 | 8+300 | Protection work at sinckage area..check by E.E sir | Mukesh Kumar Yadav | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
13. | 27-10-2016 | 4+225 | Thickness checking by E.E sir | Mukesh Kumar Yadav | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
14. | 27-10-2016 | 0+050 | Seal coat work and E.E sahab site visit | Mukesh Kumar Yadav | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
15. | 26-10-2016 | Ch 2.950 | Temperature checking of seal coat | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
16. | 26-10-2016 | Ch 2.950 | Thickness checking of pc | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
17. | 23-10-2016 | 4+200 | Rolling after seal coat work | Mukesh Kumar Yadav | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
18. | 23-10-2016 | 4+050 | P. M. C work progress | Mukesh Kumar Yadav | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
19. | 21-10-2016 | 3+900 | Tack coat | Mukesh Kumar Yadav | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
20. | 21-10-2016 | 3+900 | PMC work progress | Mukesh Kumar Yadav | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
|
|