Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/36/RD/083 Agreement signed
Project: UDRP-RB Package No.: 94 Package Name: UDRP/PWD/02/36/RD/083 Sanction Cost: 622.60  lakhs
District: Chamoli Block: Karnaprayag Constituency: Karanprayag Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  1225   Bagoli Koti Motor Road (11.200 KM.) (completed)
Procurement:
Package No.: 94        Package Name: UDRP/PWD/02/36/RD/083        Tender Date: 18-02-2015        Current Status: Agreement signed        Achieved on Date: 04-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/36/RD/083        Contractor Name: Universal Associates       
Start Date: 11-06-2015        Intended Completion Date: 08-11-2016        Original End Date:  10-09-2016
Total Bond Cost: 55011028.02 (550.11 lakhs)        Variation Cost: 7233682.16 (72.34 lakhs)     Hence Total Bond Cost is   62244710.18 (622.45 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence11.20 KM31.4711.20 KM11.20 KM6.9231.47
2.R/Wall, B/ Wall Type Protection works2575.00 m120.082575.00 m2575.00 m26.4120.08
3.G-20.30 KM3.210.30 KM0.30 KM0.713.21
4.G-32.45 KM18.232.45 KM2.45 KM4.0118.23
5.PC/CC i/c Prime Coat, Tack Coat11.20 KM124.1011.20 KM11.20 KM27.29124.10
6.Cause Way7.00 No21.507.00 No7.00 No4.7321.50
7.Culverts/Scupper 32.00 No72.0432.00 No32.00 No15.8472.04
8.longitudinal Drain10510.00 m48.2210510.00 m10510.00 m10.648.22
9.Crash Barrier0.00 m0.000.00 m0.00 m00.00
10.Parapet500.00 No13.27500.00 No500.00 No2.9213.27
11.Road Furniture249.00 No2.66249.00 No249.00 No0.582.66
Total Amount: 454.78 100   454.78
Remarks: No Remarks       Work Program Made On: 13-07-2015       Updation of work program on: 06-06-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.24-September-201552.71  lakhs
2.30-October-201575.34  lakhs
3.30-January-201686.93  lakhs
4.29-February-201645.02  lakhs
5.28-March-201626.84  lakhs
6.02-May-201682.83  lakhs
7.29-June-201624.53  lakhs
8.30-June-201651.44  lakhs
9.31-August-201627.27  lakhs
10.18-October-201644.48  lakhs
11.26-October-201656.84  lakhs
12.31-March-201748.20  lakhs
Total 622.43  lakhs
% Payment 100 %
Advance Amount:  132.83  lakhs        Recovered Amount:  132.83  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 371     No. of Test Done : 399      No. of Test Passed : 364      No. of Test Failed : 35   Test report of this package
Number of Pics Available on Web Repository: 289
Number of Notice(s) issued: 74

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-01-2017Ch 8.585Measurement checking by EE sirKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
2.27-01-2017Ch 9.900Sign boardKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
3.12-01-20170.015Scupper abutment work in progressAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
4.12-01-20170.015Rejected scupper abutmentAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
5.30-11-20166.025Delinator and edge stone fixedAshwani KumarREDSC4 R&B WB Chamoli See Pic
6.25-11-2016Ch 0.100Path way for movement of villagers connection road to griddle pathKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
7.25-11-2016Ch 7.330Patch workKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
8.17-11-20164+420Painting on parapetMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
9.17-11-20160+100Parapet white wash completeMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
10.16-11-20163+825Extension joint seeling of causewayAjay Narayan PandeyREDSC1 R&B WB Chamoli See Pic
11.16-11-20160+119Parapete penting.Ajay Narayan PandeyREDSC1 R&B WB Chamoli See Pic
12.27-10-20168+300Protection work at sinckage area..check by E.E sirMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
13.27-10-20164+225Thickness checking by E.E sirMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
14.27-10-20160+050Seal coat work and E.E sahab site visitMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
15.26-10-2016Ch 2.950Temperature checking of seal coatKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
16.26-10-2016Ch 2.950Thickness checking of pcKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
17.23-10-20164+200Rolling after seal coat workMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
18.23-10-20164+050P. M. C work progressMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
19.21-10-20163+900Tack coatMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
20.21-10-20163+900PMC work progressMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic