Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/37/RD/082 Agreement signed
Project: UDRP-RB Package No.: 93 Package Name: UDRP/PWD/02/37/RD/082 Sanction Cost: 622.19  lakhs
District: Chamoli Block: Narain Bagar Constituency: Tharali Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  1259   Narayanbagar-Kaub Motor Road (6.350 KM.) (completed)
Procurement:
Package No.: 93        Package Name: UDRP/PWD/02/37/RD/082        Tender Date: 18-02-2015        Current Status: Agreement signed        Achieved on Date: 04-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/37/RD/082        Contractor Name: Universal Associates       
Start Date: 11-06-2015        Intended Completion Date: 31-05-2017        Original End Date:  10-09-2016
Total Bond Cost: 53596905.6 (535.97 lakhs)        Variation Cost: 8005875.11 (80.06 lakhs)     Hence Total Bond Cost is   61602780.71 (616.03 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 348374 for 13 days        LD Analysis for Milestone2: calculated LD is Rs 1795466 for 67 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence6.35 KM14.426.35 KM6.35 KM3.1914.42
2.R/Wall, B/ Wall Type Protection works1760.00 m130.881760.00 m1760.00 m28.96130.88
3.G-26.35 KM68.2012.70 KM12.70 KM15.0968.20
4.G-36.35 KM48.736.35 KM6.35 KM10.7848.73
5.PC/CC i/c Prime Coat, Tack Coat6.35 KM79.386.35 KM6.35 KM17.5779.38
6.Cause Way9.00 No10.019.00 No9.00 No2.2210.01
7.Culverts/Scupper 34.00 No64.8434.00 No34.00 No14.3564.84
8.longitudinal Drain6350.00 m26.926350.00 m6350.00 m5.9626.92
9.Crash Barrier0.00 m0.000.00 m0.00 m00.00
10.Parapet600.00 No6.29600.00 No600.00 No1.396.29
11.Road Furniture182.00 No2.22182.00 No182.00 No0.492.22
Total Amount: 451.89 100   451.89
Remarks: No Remarks       Work Program Made On: 13-07-2015       Updation of work program on: 23-09-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.24-September-201545.43  lakhs
2.01-October-201517.05  lakhs
3.31-January-2016103.11  lakhs
4.04-March-201649.24  lakhs
5.28-March-201613.24  lakhs
6.02-May-201630.33  lakhs
7.29-June-201612.20  lakhs
8.30-June-201616.56  lakhs
9.30-August-201617.97  lakhs
10.30-September-201651.73  lakhs
11.25-January-201722.41  lakhs
12.22-March-201743.94  lakhs
13.31-March-201727.96  lakhs
14.25-May-201766.95  lakhs
15.14-July-201764.14  lakhs
16.27-February-201833.78  lakhs
Total 616.04  lakhs
% Payment 100 %
Advance Amount:  86.20  lakhs        Recovered Amount:  86.20  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 279     No. of Test Done : 297      No. of Test Passed : 276      No. of Test Failed : 21   Test report of this package
Number of Pics Available on Web Repository: 74
Number of Notice(s) issued: 68

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.31-03-2017Ch 0.950Emulsion for primer of hincolKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
2.31-03-2017Ch 5.915Thickness checking of G2 G3 layer found 25 cmKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
3.25-03-2017Ch 6.180Bitumen extraction test of pcKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
4.25-03-2017Ch 6.180Laying of pcKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
5.25-03-2017Ch 6.212Rolling of seal coatKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
6.18-03-2017chainage 0+640Road width checking found 6.10 mSohanbir SinghJEUDRP R&B Chamoli See Pic
7.07-02-2017Xh 5.250Screening material over G3Kirti Vardhan NegiAEDEA WB Gopeshwar See Pic
8.30-01-2017Ch 5.250Rolling of G3Kirti Vardhan NegiAEDEA WB Gopeshwar See Pic
9.30-01-2017Ch 3.675Checking of measurements by Ee sirKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
10.23-09-20160.225Checking of G2 layer by CE sirKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
11.25-06-2016C.h. 2.250Hume pipeKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
12.25-06-2016Ch2.250Hume pipeKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
13.14-06-20164+000G2 lst layerMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
14.11-06-2016Ch 0.825AIV test FOR G2 materialKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
15.11-06-2016C.h. 5 775Hume pipeKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
16.11-06-2016Ch 5.750Hume pipeKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
17.11-06-2016Ch 3.2005 m span culvertKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
18.09-03-20165.625G2Sudhir KumarREDSC1 R&B WB Chamoli See Pic
19.09-03-20160.140Checking of superelevationSudhir KumarREDSC1 R&B WB Chamoli See Pic
20.09-03-20165.825scupperVinod Singh ChauhanJEUDRP R&B Gopeshwar See Pic