UDRP/PWD/02/37/RD/082
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
93 |
Package Name: |
UDRP/PWD/02/37/RD/082 |
Sanction Cost: |
622.19 lakhs |
District: |
Chamoli |
Block: |
Narain Bagar |
Constituency: |
Tharali |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 1259 Narayanbagar-Kaub Motor Road (6.350 KM.) (completed) |
|
Procurement: |
Package No.: 93
Package Name: UDRP/PWD/02/37/RD/082
Tender Date: 18-02-2015
Current Status: Agreement signed
Achieved on Date: 04-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/37/RD/082
Contractor Name: Universal Associates
|
Start Date: 11-06-2015
Intended Completion Date: 31-05-2017
Original End Date: 10-09-2016
|
Total Bond Cost: 53596905.6 (535.97 lakhs)
Variation Cost: 8005875.11 (80.06 lakhs) Hence Total Bond Cost is 61602780.71 (616.03 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 348374 for 13 days
LD Analysis for Milestone2: calculated LD is Rs 1795466 for 67 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 6.35 KM | 14.42 | 6.35 KM | 6.35 KM | 3.19 | 14.42 | 2. | R/Wall, B/ Wall Type Protection works | 1760.00 m | 130.88 | 1760.00 m | 1760.00 m | 28.96 | 130.88 | 3. | G-2 | 6.35 KM | 68.20 | 12.70 KM | 12.70 KM | 15.09 | 68.20 | 4. | G-3 | 6.35 KM | 48.73 | 6.35 KM | 6.35 KM | 10.78 | 48.73 | 5. | PC/CC i/c Prime Coat, Tack Coat | 6.35 KM | 79.38 | 6.35 KM | 6.35 KM | 17.57 | 79.38 | 6. | Cause Way | 9.00 No | 10.01 | 9.00 No | 9.00 No | 2.22 | 10.01 | 7. | Culverts/Scupper | 34.00 No | 64.84 | 34.00 No | 34.00 No | 14.35 | 64.84 | 8. | longitudinal Drain | 6350.00 m | 26.92 | 6350.00 m | 6350.00 m | 5.96 | 26.92 | 9. | Crash Barrier | 0.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 10. | Parapet | 600.00 No | 6.29 | 600.00 No | 600.00 No | 1.39 | 6.29 | 11. | Road Furniture | 182.00 No | 2.22 | 182.00 No | 182.00 No | 0.49 | 2.22 |
Total Amount: |
451.89 |
|
100 |
451.89 |
|
Remarks:
No Remarks
Work Program Made On:
13-07-2015
Updation of work program on:
23-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 24-September-2015 | 45.43 lakhs |
2. | 01-October-2015 | 17.05 lakhs |
3. | 31-January-2016 | 103.11 lakhs |
4. | 04-March-2016 | 49.24 lakhs |
5. | 28-March-2016 | 13.24 lakhs |
6. | 02-May-2016 | 30.33 lakhs |
7. | 29-June-2016 | 12.20 lakhs |
8. | 30-June-2016 | 16.56 lakhs |
9. | 30-August-2016 | 17.97 lakhs |
10. | 30-September-2016 | 51.73 lakhs |
11. | 25-January-2017 | 22.41 lakhs |
12. | 22-March-2017 | 43.94 lakhs |
13. | 31-March-2017 | 27.96 lakhs |
14. | 25-May-2017 | 66.95 lakhs |
15. | 14-July-2017 | 64.14 lakhs |
16. | 27-February-2018 | 33.78 lakhs |
Total |
616.04 lakhs |
% Payment |
100 % |
|
Advance Amount: 86.20 lakhs
Recovered Amount: 86.20 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 74 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 31-03-2017 | Ch 0.950 | Emulsion for primer of hincol | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
2. | 31-03-2017 | Ch 5.915 | Thickness checking of G2 G3 layer found 25 cm | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
3. | 25-03-2017 | Ch 6.180 | Bitumen extraction test of pc | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
4. | 25-03-2017 | Ch 6.180 | Laying of pc | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
5. | 25-03-2017 | Ch 6.212 | Rolling of seal coat | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
6. | 18-03-2017 | chainage 0+640 | Road width checking found 6.10 m | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
7. | 07-02-2017 | Xh 5.250 | Screening material over G3 | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
8. | 30-01-2017 | Ch 5.250 | Rolling of G3 | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
9. | 30-01-2017 | Ch 3.675 | Checking of measurements by Ee sir | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
10. | 23-09-2016 | 0.225 | Checking of G2 layer by CE sir | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
11. | 25-06-2016 | C.h. 2.250 | Hume pipe | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
12. | 25-06-2016 | Ch2.250 | Hume pipe | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
13. | 14-06-2016 | 4+000 | G2 lst layer | Mukesh Kumar Yadav | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
14. | 11-06-2016 | Ch 0.825 | AIV test FOR G2 material | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
15. | 11-06-2016 | C.h. 5 775 | Hume pipe | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
16. | 11-06-2016 | Ch 5.750 | Hume pipe | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
17. | 11-06-2016 | Ch 3.200 | 5 m span culvert | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
18. | 09-03-2016 | 5.625 | G2 | Sudhir Kumar | RE | DSC1 R&B WB Chamoli | See Pic |
19. | 09-03-2016 | 0.140 | Checking of superelevation | Sudhir Kumar | RE | DSC1 R&B WB Chamoli | See Pic |
20. | 09-03-2016 | 5.825 | scupper | Vinod Singh Chauhan | JE | UDRP R&B Gopeshwar | See Pic |
|
|