Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/08/RD/081 Agreement signed
Project: UDRP-RB Package No.: 92 Package Name: UDRP/PWD/02/08/RD/081 Sanction Cost: 359.79  lakhs
District: Chamoli Block: Joshimath Constituency: Badrinath Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 2
Subproject in this package
1  1217   Salor - Dungra MR (6.000 KM.) (completed)
2  1297   Raitoli-Nargoli-Kamiyar motor road (1.000 KM.) (completed)
Procurement:
Package No.: 92        Package Name: UDRP/PWD/02/08/RD/081        Tender Date: 23-05-2015        Current Status: Agreement signed        Achieved on Date: 31-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/08/RD/081        Contractor Name: Raina Construction       
Start Date: 07-08-2015        Intended Completion Date: 31-03-2018        Original End Date:  06-11-2016
Total Bond Cost: 31526435.26 (315.26 lakhs)        Variation Cost: 2442431.62 (24.42 lakhs)     Hence Total Bond Cost is   33968866.88 (339.69 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2616658 for 166 days        LD Analysis for Milestone2: calculated LD is Rs 4902293 for 311 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence7.00 KM12.167.00 KM7.00 KM4.1312.16
2.R/Wall, B/ Wall Type Protection works711.00 m56.19711.00 m711.00 m19.0956.19
3.G-24.10 KM24.224.10 KM4.10 KM8.3624.22
4.G-36.50 KM42.296.50 KM6.50 KM14.442.29
5.PC/CC i/c Prime Coat, Tack Coat6.80 KM90.806.80 KM6.80 KM30.8590.80
6.Culverts/Scupper 8.00 No45.108.00 No8.00 No15.3645.10
7.longitudinal Drain7000.00 m16.967000.00 m7000.00 m5.8116.96
8.Parapet125.00 No2.73125.00 No125.00 No0.942.73
9.Road Furniture170.00 No3.14170.00 No170.00 No1.083.14
Total Amount: 293.59 100   293.59
Remarks: No Remarks       Work Program Made On: 28-09-2015       Updation of work program on: 17-04-2018      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.05-December-201520.55  lakhs
2.29-February-201613.08  lakhs
3.11-May-20160.06  lakhs
4.30-June-201636.65  lakhs
5.30-September-201640.45  lakhs
6.26-October-201613.54  lakhs
7.31-December-20169.74  lakhs
8.08-March-20177.93  lakhs
9.25-May-201732.52  lakhs
10.28-July-201726.09  lakhs
11.16-October-20178.01  lakhs
12.17-October-20170.43  lakhs
13.18-December-201763.00  lakhs
14.17-February-201816.05  lakhs
15.15-May-201811.71  lakhs
16.07-June-201821.82  lakhs
17.13-September-201818.47  lakhs
Total 340.1  lakhs
% Payment 100.12 %
Advance Amount:  12.00  lakhs        Recovered Amount:  12.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 78     No. of Test Done : 85      No. of Test Passed : 75      No. of Test Failed : 10   Test report of this package
Number of Pics Available on Web Repository: 127
Number of Notice(s) issued: 94

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-11-20173.300Consultation with local people Mr kuldip Chuhan regarding metal crash barriersAshwani KumarREDSC4 R&B WB Chamoli See Pic
2.23-11-20173.400Rolling on seal coatAshwani KumarREDSC4 R&B WB Chamoli See Pic
3.23-11-20173.400Laying of seal coatAshwani KumarREDSC4 R&B WB Chamoli See Pic
4.23-11-20173.280OGPC thickness checking by EE Gopeshwar thickness found 25mmAshwani KumarREDSC4 R&B WB Chamoli See Pic
5.23-11-20170.640Width checking by EE Gopeshwar width found 3.75mAshwani KumarREDSC4 R&B WB Chamoli See Pic
6.20-11-20170.400Quality of OGPC Work is satisfactoryAshwani KumarREDSC4 R&B WB Chamoli See Pic
7.20-11-20170.300Proposal of tree cutting still pendingAshwani KumarREDSC4 R&B WB Chamoli See Pic
8.18-11-20174.260Checking of road width found 4.100Ashwani KumarREDSC4 R&B WB Chamoli See Pic
9.01-11-20173.300Checking of road width 6.0mAshwani KumarREDSC4 R&B WB Chamoli See Pic
10.03-10-20173.400WBM G3 layer work in progress but thickness or layer is only 50 mm. So, instruction given to contractor to rectify WBMG3 layerAshwani KumarREDSC4 R&B WB Chamoli See Pic
11.17-07-20174.300Road closed due to heavy land slideAshwani KumarREDSC4 R&B WB Chamoli See Pic
12.15-05-20171.600Undulation checking found 10mmAshwani KumarREDSC4 R&B WB Chamoli See Pic
13.08-02-20170.640Stone for WBM G2 rejected due to flakinessAshwani KumarREDSC4 R&B WB Chamoli See Pic
14.07-02-2017Ch 0.530Rejected G2 stoneKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
15.27-01-2017Site LabTesting for AIV passedPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
16.05-01-20171.050Thickness checking of G2 &G3 Layer found 150mmAshwani KumarREDSC4 R&B WB Chamoli See Pic
17.27-12-2016Ch-0.700Hillside cuttingPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
18.27-12-20161.675C type drainPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
19.13-12-2016Ch-3.150Road width checking after Hill cuttingPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
20.13-12-2016Ch-3.280Gradation for g2Pramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic