UDRP/PWD/02/08/RD/081
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
92 |
Package Name: |
UDRP/PWD/02/08/RD/081 |
Sanction Cost: |
359.79 lakhs |
District: |
Chamoli |
Block: |
Joshimath |
Constituency: |
Badrinath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 1217 Salor - Dungra MR (6.000 KM.) (completed) | 2 1297 Raitoli-Nargoli-Kamiyar motor road (1.000 KM.) (completed) |
|
Procurement: |
Package No.: 92
Package Name: UDRP/PWD/02/08/RD/081
Tender Date: 23-05-2015
Current Status: Agreement signed
Achieved on Date: 31-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/08/RD/081
Contractor Name: Raina Construction
|
Start Date: 07-08-2015
Intended Completion Date: 31-03-2018
Original End Date: 06-11-2016
|
Total Bond Cost: 31526435.26 (315.26 lakhs)
Variation Cost: 2442431.62 (24.42 lakhs) Hence Total Bond Cost is 33968866.88 (339.69 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2616658 for 166 days
LD Analysis for Milestone2: calculated LD is Rs 4902293 for 311 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 7.00 KM | 12.16 | 7.00 KM | 7.00 KM | 4.13 | 12.16 | 2. | R/Wall, B/ Wall Type Protection works | 711.00 m | 56.19 | 711.00 m | 711.00 m | 19.09 | 56.19 | 3. | G-2 | 4.10 KM | 24.22 | 4.10 KM | 4.10 KM | 8.36 | 24.22 | 4. | G-3 | 6.50 KM | 42.29 | 6.50 KM | 6.50 KM | 14.4 | 42.29 | 5. | PC/CC i/c Prime Coat, Tack Coat | 6.80 KM | 90.80 | 6.80 KM | 6.80 KM | 30.85 | 90.80 | 6. | Culverts/Scupper | 8.00 No | 45.10 | 8.00 No | 8.00 No | 15.36 | 45.10 | 7. | longitudinal Drain | 7000.00 m | 16.96 | 7000.00 m | 7000.00 m | 5.81 | 16.96 | 8. | Parapet | 125.00 No | 2.73 | 125.00 No | 125.00 No | 0.94 | 2.73 | 9. | Road Furniture | 170.00 No | 3.14 | 170.00 No | 170.00 No | 1.08 | 3.14 |
Total Amount: |
293.59 |
|
100 |
293.59 |
|
Remarks:
No Remarks
Work Program Made On:
28-09-2015
Updation of work program on:
17-04-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 05-December-2015 | 20.55 lakhs |
2. | 29-February-2016 | 13.08 lakhs |
3. | 11-May-2016 | 0.06 lakhs |
4. | 30-June-2016 | 36.65 lakhs |
5. | 30-September-2016 | 40.45 lakhs |
6. | 26-October-2016 | 13.54 lakhs |
7. | 31-December-2016 | 9.74 lakhs |
8. | 08-March-2017 | 7.93 lakhs |
9. | 25-May-2017 | 32.52 lakhs |
10. | 28-July-2017 | 26.09 lakhs |
11. | 16-October-2017 | 8.01 lakhs |
12. | 17-October-2017 | 0.43 lakhs |
13. | 18-December-2017 | 63.00 lakhs |
14. | 17-February-2018 | 16.05 lakhs |
15. | 15-May-2018 | 11.71 lakhs |
16. | 07-June-2018 | 21.82 lakhs |
17. | 13-September-2018 | 18.47 lakhs |
Total |
340.1 lakhs |
% Payment |
100.12 % |
|
Advance Amount: 12.00 lakhs
Recovered Amount: 12.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 127 |
Number of Notice(s) issued: 94 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-11-2017 | 3.300 | Consultation with local people Mr kuldip Chuhan regarding metal crash barriers | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
2. | 23-11-2017 | 3.400 | Rolling on seal coat | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
3. | 23-11-2017 | 3.400 | Laying of seal coat | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
4. | 23-11-2017 | 3.280 | OGPC thickness checking by EE Gopeshwar thickness found 25mm | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
5. | 23-11-2017 | 0.640 | Width checking by EE Gopeshwar width found 3.75m | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
6. | 20-11-2017 | 0.400 | Quality of OGPC Work is satisfactory | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
7. | 20-11-2017 | 0.300 | Proposal of tree cutting still pending | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
8. | 18-11-2017 | 4.260 | Checking of road width found 4.100 | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
9. | 01-11-2017 | 3.300 | Checking of road width 6.0m | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
10. | 03-10-2017 | 3.400 | WBM G3 layer work in progress but thickness or layer is only 50 mm. So, instruction given to contractor to rectify WBMG3 layer | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
11. | 17-07-2017 | 4.300 | Road closed due to heavy land slide | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
12. | 15-05-2017 | 1.600 | Undulation checking found 10mm | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
13. | 08-02-2017 | 0.640 | Stone for WBM G2 rejected due to flakiness | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
14. | 07-02-2017 | Ch 0.530 | Rejected G2 stone | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
15. | 27-01-2017 | Site Lab | Testing for AIV passed | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
16. | 05-01-2017 | 1.050 | Thickness checking of G2 &G3 Layer found 150mm | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
17. | 27-12-2016 | Ch-0.700 | Hillside cutting | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
18. | 27-12-2016 | 1.675 | C type drain | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
19. | 13-12-2016 | Ch-3.150 | Road width checking after Hill cutting | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
20. | 13-12-2016 | Ch-3.280 | Gradation for g2 | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
|
|