Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/08/RD/080 Agreement signed
Project: UDRP-RB Package No.: 91 Package Name: UDRP/PWD/02/08/RD/080 Sanction Cost: 164.11  lakhs
District: Chamoli Block: Dasholi Constituency: Tharali Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  1265   Pursari Palethi Sartoli (1.000 KM.) (completed)
Procurement:
Package No.: 91        Package Name: UDRP/PWD/02/08/RD/080        Tender Date: 18-02-2015        Current Status: Agreement signed        Achieved on Date: 05-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/08/RD/080        Contractor Name: Dream Real Infra       
Start Date: 12-06-2015        Intended Completion Date: 11-04-2017        Original End Date:  11-09-2016
Total Bond Cost: 10606269.9 (106.06 lakhs)        Variation Cost: 4998077.98 (49.98 lakhs)     Hence Total Bond Cost is   15604347.88 (156.04 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 111363 for 21 days        LD Analysis for Milestone2: calculated LD is Rs 1309841 for 247 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.50 KM7.880.50 KM0.50 KM147.88
2.R/Wall, B/ Wall Type Protection works400.00 m40.53400.00 m400.00 m72.0240.53
3.G-20.00 KM0.000.00 KM0.00 KM00.00
4.G-30.00 KM0.000.00 KM0.00 KM00.00
5.PC/CC i/c Prime Coat, Tack Coat0.00 KM0.000.00 KM0.00 KM00.00
6.Culverts/Scupper 4.00 No6.444.00 No4.00 No11.456.44
7.longitudinal Drain75.00 m1.2175.00 m75.00 m2.141.21
8.Parapet0.00 No0.000.00 No0.00 No00.00
9.Road Furniture2.00 No0.222.00 No2.00 No0.390.22
Total Amount: 56.28 100   56.28
Remarks: No Remarks       Work Program Made On: 14-07-2015       Updation of work program on: 17-11-2018      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-October-201513.66  lakhs
2.24-December-201512.80  lakhs
3.23-January-20164.38  lakhs
4.11-May-20169.54  lakhs
5.30-September-20165.46  lakhs
6.30-December-20168.50  lakhs
7.18-September-20183.95  lakhs
Total 58.29  lakhs
% Payment 37.36 %
Advance Amount:  12.20  lakhs        Recovered Amount:  12.20  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 139     No. of Test Done : 157      No. of Test Passed : 140      No. of Test Failed : 17   Test report of this package
Number of Pics Available on Web Repository: 54
Number of Notice(s) issued: 96

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.14-04-2017Ch 2.300Bitumen content test of pc found 4 percentKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
2.14-04-2017Ch 0.550Pc layingKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
3.14-04-2017Ch 0.525Pc layingKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
4.14-04-2017C.h 0 .100Checking of thickness of pcKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
5.08-03-2017Ch-0.350Site visitPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
6.31-10-2016Ch0.325W/cPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
7.28-10-20160.325Wire Crates work in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
8.23-10-20160.000S.E. Sir visit at purshari sitePiyush MishraJEUDRP R&B Gopeshwar See Pic
9.23-10-2016300Site visit by geologist sirPiyush MishraJEUDRP R&B Gopeshwar See Pic
10.19-10-2016750Puccka drainPiyush MishraJEUDRP R&B Gopeshwar See Pic
11.19-10-2016300Shrinking zone at purshari sitePiyush MishraJEUDRP R&B Gopeshwar See Pic
12.19-10-2016+250W/C work at shrinking areaPiyush MishraJEUDRP R&B Gopeshwar See Pic
13.15-10-2016Ch-0.78024/09/16 after complete ID no 23502 we have maintend the slope of wall and the interlocking of stone masonry and bad quality stone removed and good workmanshipPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
14.15-10-2016Ch-0.300Hillside cuttingPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
15.26-09-2016Ch-0.780Retaining wall RR.Dry work in progressPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
16.06-08-2016Ch-0.750Layout for Retaining wallPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
17.04-08-2016Ch-0.650Hillside cuttingPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
18.20-06-2016Ch -0.650Causeway pccPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
19.16-06-2016Ch-0.650Causeway kharanjaPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
20.01-06-20160.100WBM G2 layerAshwani KumarREDSC4 R&B WB Chamoli See Pic