Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/38/RD/009 Agreement signed
Project: UDRP-RB Package No.: 9 Package Name: UDRP/PWD/02/38/RD/009 Sanction Cost: 1625.43  lakhs
District: Chamoli Block: Karnaprayag Constituency: Karanprayag Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  1219   Sonla - Kandara - Maikhura Silangi MR (36.000 KM.) (completed)
Procurement:
Package No.: 9        Package Name: UDRP/PWD/02/38/RD/009        Tender Date: 01-02-2014        Current Status: Agreement signed        Achieved on Date: 26-04-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/38/RD/009        Contractor Name: Ramnarayan.       
Start Date: 26-04-2014        Intended Completion Date: 28-05-2017        Original End Date:  26-07-2015
Total Bond Cost: 123395603.92 (1233.96 lakhs)        Variation Cost: 35350130.57 (353.5 lakhs)     Hence Total Bond Cost is   158745734.49 (1587.46 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 3455088 for 56 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence7.00 KM135.147.00 KM7.00 KM9.16135.14
2.R/Wall, B/ Wall Type Protection works5588.00 m460.635588.00 m5588.00 m31.21460.63
3.GSB/RBI/G-17.39 KM33.177.39 KM7.39 KM2.2533.17
4.G-211.00 KM36.9611.00 KM11.00 KM2.536.96
5.G-311.00 KM41.7211.00 KM11.00 KM2.8341.72
6.PC/CC i/c Prime Coat, Tack Coat32.50 KM361.2832.50 KM32.50 KM24.48361.28
7.Cause Way8.00 No17.488.00 No8.00 No1.1817.48
8.Culverts/Scupper 68.00 No124.1368.00 No68.00 No8.41124.13
9.longitudinal Drain32500.00 m98.6432500.00 m32500.00 m6.6898.64
10.Crash Barrier602.00 m70.78602.00 m602.00 m4.870.78
11.Parapet1976.00 No88.271976.00 No1976.00 No5.9888.27
12.Road Furniture410.00 No7.92410.00 No410.00 No0.547.92
Total Amount: 1476.12 100   1476.12
Remarks: No Remarks       Work Program Made On: 19-06-2014       Updation of work program on: 23-09-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-September-201463.27  lakhs
2.06-December-201452.73  lakhs
3.31-December-201436.70  lakhs
4.12-February-201538.22  lakhs
5.02-March-201518.17  lakhs
6.18-March-201518.95  lakhs
7.28-March-20155.72  lakhs
8.21-April-201514.98  lakhs
9.03-June-201534.59  lakhs
10.11-September-201548.19  lakhs
11.28-September-2015115.04  lakhs
12.19-October-201527.87  lakhs
13.31-October-201589.28  lakhs
14.30-November-201560.95  lakhs
15.15-January-201612.33  lakhs
16.23-January-201651.14  lakhs
17.28-February-201629.51  lakhs
18.30-March-201652.62  lakhs
19.02-May-201640.39  lakhs
20.11-May-2016137.15  lakhs
21.30-June-2016101.48  lakhs
22.21-July-201652.43  lakhs
23.24-August-201624.28  lakhs
24.30-August-20160.78  lakhs
25.26-October-201645.33  lakhs
26.30-December-201656.82  lakhs
27.25-January-201732.89  lakhs
28.10-February-201718.92  lakhs
29.23-March-201713.13  lakhs
30.20-May-201755.39  lakhs
31.17-July-201737.33  lakhs
32.18-December-201763.07  lakhs
33.24-April-201852.00  lakhs
34.28-August-201811.22  lakhs
Total 1512.87  lakhs
% Payment 95.3 %
Advance Amount:  195.66  lakhs        Recovered Amount:  195.66  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 613     No. of Test Done : 633      No. of Test Passed : 544      No. of Test Failed : 89   Test report of this package
Number of Pics Available on Web Repository: 675
Number of Notice(s) issued: 109

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.03-08-201720.125Site inspection SEAshwani KumarREDSC4 R&B WB Chamoli See Pic
2.17-07-201714.300Ashwani KumarREDSC4 R&B WB Chamoli See Pic
3.02-12-201619.010Road edge damaged due to cutting of road by Airtel instead of hillsideAshwani KumarREDSC4 R&B WB Chamoli See Pic
4.02-12-201611.425Road edge cutting by Airtel instead of hillsideAshwani KumarREDSC4 R&B WB Chamoli See Pic
5.02-12-2016Ch. 19.025Pc edge cutting + drain damageAnkur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
6.30-11-2016Ch. 5.850Slip clearanceAnkur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
7.30-11-2016Ch. 6.300Slip clearanceAnkur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
8.30-11-2016Ch. 7.150Slip clearanceAnkur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
9.30-11-2016Ch. 9.925Way for templeAnkur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
10.21-11-2016CH 10.100Causeway damage due to laying of ducts by AirtelJayendra PundirSite SupervisorDSC1 R&B WB Chamoli See Pic
11.18-11-201612.500Kc drain dismentlingPiyush MishraJEUDRP R&B Gopeshwar See Pic
12.17-11-2016Ch. 12. 550Pc + KC drain damageAnkur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
13.15-11-2016Ch. 28. 285Plum work is going...Ankur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
14.09-11-201628.200P.c work at ch 28.200Piyush MishraJEUDRP R&B Gopeshwar See Pic
15.09-11-201611.300Diffuct cuttingPiyush MishraJEUDRP R&B Gopeshwar See Pic
16.09-11-2016550Parapet white washingPiyush MishraJEUDRP R&B Gopeshwar See Pic
17.09-11-2016Ch.11. 350Patch work is going on.....Ankur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
18.08-11-2016Ch.9. 950Profile correction for patch work.......Ankur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
19.07-11-201611,800DeefatDeepak RawatContractor Site SupervisorDSC1 R&B WB Chamoli See Pic
20.07-11-2016Ch.3,525Birecha.ropanDeepak RawatContractor Site SupervisorDSC1 R&B WB Chamoli See Pic