UDRP/PWD/02/38/RD/009
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
9 |
Package Name: |
UDRP/PWD/02/38/RD/009 |
Sanction Cost: |
1625.43 lakhs |
District: |
Chamoli |
Block: |
Karnaprayag |
Constituency: |
Karanprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 1219 Sonla - Kandara - Maikhura Silangi MR (36.000 KM.) (completed) |
|
Procurement: |
Package No.: 9
Package Name: UDRP/PWD/02/38/RD/009
Tender Date: 01-02-2014
Current Status: Agreement signed
Achieved on Date: 26-04-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/38/RD/009
Contractor Name: Ramnarayan.
|
Start Date: 26-04-2014
Intended Completion Date: 28-05-2017
Original End Date: 26-07-2015
|
Total Bond Cost: 123395603.92 (1233.96 lakhs)
Variation Cost: 35350130.57 (353.5 lakhs) Hence Total Bond Cost is 158745734.49 (1587.46 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 3455088 for 56 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 7.00 KM | 135.14 | 7.00 KM | 7.00 KM | 9.16 | 135.14 | 2. | R/Wall, B/ Wall Type Protection works | 5588.00 m | 460.63 | 5588.00 m | 5588.00 m | 31.21 | 460.63 | 3. | GSB/RBI/G-1 | 7.39 KM | 33.17 | 7.39 KM | 7.39 KM | 2.25 | 33.17 | 4. | G-2 | 11.00 KM | 36.96 | 11.00 KM | 11.00 KM | 2.5 | 36.96 | 5. | G-3 | 11.00 KM | 41.72 | 11.00 KM | 11.00 KM | 2.83 | 41.72 | 6. | PC/CC i/c Prime Coat, Tack Coat | 32.50 KM | 361.28 | 32.50 KM | 32.50 KM | 24.48 | 361.28 | 7. | Cause Way | 8.00 No | 17.48 | 8.00 No | 8.00 No | 1.18 | 17.48 | 8. | Culverts/Scupper | 68.00 No | 124.13 | 68.00 No | 68.00 No | 8.41 | 124.13 | 9. | longitudinal Drain | 32500.00 m | 98.64 | 32500.00 m | 32500.00 m | 6.68 | 98.64 | 10. | Crash Barrier | 602.00 m | 70.78 | 602.00 m | 602.00 m | 4.8 | 70.78 | 11. | Parapet | 1976.00 No | 88.27 | 1976.00 No | 1976.00 No | 5.98 | 88.27 | 12. | Road Furniture | 410.00 No | 7.92 | 410.00 No | 410.00 No | 0.54 | 7.92 |
Total Amount: |
1476.12 |
|
100 |
1476.12 |
|
Remarks:
No Remarks
Work Program Made On:
19-06-2014
Updation of work program on:
23-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-September-2014 | 63.27 lakhs |
2. | 06-December-2014 | 52.73 lakhs |
3. | 31-December-2014 | 36.70 lakhs |
4. | 12-February-2015 | 38.22 lakhs |
5. | 02-March-2015 | 18.17 lakhs |
6. | 18-March-2015 | 18.95 lakhs |
7. | 28-March-2015 | 5.72 lakhs |
8. | 21-April-2015 | 14.98 lakhs |
9. | 03-June-2015 | 34.59 lakhs |
10. | 11-September-2015 | 48.19 lakhs |
11. | 28-September-2015 | 115.04 lakhs |
12. | 19-October-2015 | 27.87 lakhs |
13. | 31-October-2015 | 89.28 lakhs |
14. | 30-November-2015 | 60.95 lakhs |
15. | 15-January-2016 | 12.33 lakhs |
16. | 23-January-2016 | 51.14 lakhs |
17. | 28-February-2016 | 29.51 lakhs |
18. | 30-March-2016 | 52.62 lakhs |
19. | 02-May-2016 | 40.39 lakhs |
20. | 11-May-2016 | 137.15 lakhs |
21. | 30-June-2016 | 101.48 lakhs |
22. | 21-July-2016 | 52.43 lakhs |
23. | 24-August-2016 | 24.28 lakhs |
24. | 30-August-2016 | 0.78 lakhs |
25. | 26-October-2016 | 45.33 lakhs |
26. | 30-December-2016 | 56.82 lakhs |
27. | 25-January-2017 | 32.89 lakhs |
28. | 10-February-2017 | 18.92 lakhs |
29. | 23-March-2017 | 13.13 lakhs |
30. | 20-May-2017 | 55.39 lakhs |
31. | 17-July-2017 | 37.33 lakhs |
32. | 18-December-2017 | 63.07 lakhs |
33. | 24-April-2018 | 52.00 lakhs |
34. | 28-August-2018 | 11.22 lakhs |
Total |
1512.87 lakhs |
% Payment |
95.3 % |
|
Advance Amount: 195.66 lakhs
Recovered Amount: 195.66 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 675 |
Number of Notice(s) issued: 109 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 03-08-2017 | 20.125 | Site inspection SE | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
2. | 17-07-2017 | 1 | 4.300 | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
3. | 02-12-2016 | 19.010 | Road edge damaged due to cutting of road by Airtel instead of hillside | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
4. | 02-12-2016 | 11.425 | Road edge cutting by Airtel instead of hillside | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
5. | 02-12-2016 | Ch. 19.025 | Pc edge cutting + drain damage | Ankur Vishwas | Contractor Site Engineer | DSC1 R&B WB Chamoli | See Pic |
6. | 30-11-2016 | Ch. 5.850 | Slip clearance | Ankur Vishwas | Contractor Site Engineer | DSC1 R&B WB Chamoli | See Pic |
7. | 30-11-2016 | Ch. 6.300 | Slip clearance | Ankur Vishwas | Contractor Site Engineer | DSC1 R&B WB Chamoli | See Pic |
8. | 30-11-2016 | Ch. 7.150 | Slip clearance | Ankur Vishwas | Contractor Site Engineer | DSC1 R&B WB Chamoli | See Pic |
9. | 30-11-2016 | Ch. 9.925 | Way for temple | Ankur Vishwas | Contractor Site Engineer | DSC1 R&B WB Chamoli | See Pic |
10. | 21-11-2016 | CH 10.100 | Causeway damage due to laying of ducts by Airtel | Jayendra Pundir | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
11. | 18-11-2016 | 12.500 | Kc drain dismentling | Piyush Mishra | JE | UDRP R&B Gopeshwar | See Pic |
12. | 17-11-2016 | Ch. 12. 550 | Pc + KC drain damage | Ankur Vishwas | Contractor Site Engineer | DSC1 R&B WB Chamoli | See Pic |
13. | 15-11-2016 | Ch. 28. 285 | Plum work is going... | Ankur Vishwas | Contractor Site Engineer | DSC1 R&B WB Chamoli | See Pic |
14. | 09-11-2016 | 28.200 | P.c work at ch 28.200 | Piyush Mishra | JE | UDRP R&B Gopeshwar | See Pic |
15. | 09-11-2016 | 11.300 | Diffuct cutting | Piyush Mishra | JE | UDRP R&B Gopeshwar | See Pic |
16. | 09-11-2016 | 550 | Parapet white washing | Piyush Mishra | JE | UDRP R&B Gopeshwar | See Pic |
17. | 09-11-2016 | Ch.11. 350 | Patch work is going on..... | Ankur Vishwas | Contractor Site Engineer | DSC1 R&B WB Chamoli | See Pic |
18. | 08-11-2016 | Ch.9. 950 | Profile correction for patch work....... | Ankur Vishwas | Contractor Site Engineer | DSC1 R&B WB Chamoli | See Pic |
19. | 07-11-2016 | 11,800 | Deefat | Deepak Rawat | Contractor Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
20. | 07-11-2016 | Ch.3,525 | Birecha.ropan | Deepak Rawat | Contractor Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
|
|