Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/01/34/RD/075 Agreement signed
Project: UDRP-RB Package No.: 86 Package Name: UDRP/PWD/01/34/RD/075 Sanction Cost: 339.22  lakhs
District: Uttarkashi Block: Naugaon Constituency: Purola Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  3135   Gadh-Dewal molthat motor road (3.850 KM.) (completed)
Procurement:
Package No.: 86        Package Name: UDRP/PWD/01/34/RD/075        Tender Date: 29-12-2014        Current Status: Agreement signed        Achieved on Date: 04-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/34/RD/075        Contractor Name: People Concern Towards Social Realities       
Start Date: 11-06-2015        Intended Completion Date: 31-01-2017        Original End Date:  10-09-2016
Total Bond Cost: 30060931.63 (300.61 lakhs)        Variation Cost: 1206824.25 (12.07 lakhs)     Hence Total Bond Cost is   31267755.88 (312.68 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 420840 for 28 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence3.85 KM12.993.85 KM3.85 KM4.5212.99
2.R/Wall, B/ Wall Type Protection works2075.00 m118.962075.00 m2075.00 m41.4118.96
3.GSB/RBI/G-10.00 KM0.000.00 KM0.00 KM00.00
4.G-23.85 KM38.663.85 KM3.85 KM13.4638.66
5.G-33.85 KM27.293.85 KM3.85 KM9.527.29
6.PC/CC i/c Prime Coat, Tack Coat3.85 KM45.783.85 KM3.85 KM15.9345.78
7.Culverts/Scupper 16.00 No36.5616.00 No16.00 No12.7236.56
8.longitudinal Drain3800.00 m6.463800.00 m3800.00 m2.256.46
9.Crash Barrier0.00 m0.000.00 m0.00 m00.00
10.Parapet0.00 No0.000.00 No0.00 No00.00
11.Road Furniture13.00 No0.6213.00 No13.00 No0.220.62
Total Amount: 287.32 100   287.32
Remarks: No Remarks       Work Program Made On: 11-08-2015       Updation of work program on: 20-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.17-September-201517.00  lakhs
2.30-September-201535.63  lakhs
3.21-January-201635.89  lakhs
4.06-February-20160.06  lakhs
5.26-February-201611.58  lakhs
6.30-March-201638.78  lakhs
7.26-May-201616.19  lakhs
8.07-September-201623.63  lakhs
9.10-October-201620.73  lakhs
10.31-December-201654.06  lakhs
11.11-January-201714.20  lakhs
12.10-April-201715.24  lakhs
13.18-May-20179.69  lakhs
14.17-June-201713.62  lakhs
15.08-December-201713.28  lakhs
16.13-March-2018-8.09  lakhs
Total 311.49  lakhs
% Payment 99.62 %
Advance Amount:  121.93  lakhs        Recovered Amount:  121.97  lakhs        Balance to be Recovered  -0.04  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 227     No. of Test Done : 251      No. of Test Passed : 235      No. of Test Failed : 16   Test report of this package
Number of Pics Available on Web Repository: 218
Number of Notice(s) issued: 116

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.05-05-2017Ch 1+500Track route for VillageVijayraj SinghJEUDRP R&B Uttarkashi See Pic
2.05-05-2017Ch- 0+300Painted Parapet.Vijayraj SinghJEUDRP R&B Uttarkashi See Pic
3.01-01-20173+300Discussion regarding site issues with villagers at Garh dewalPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
4.01-12-20161+600PC thickness found OKPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
5.01-12-20161+625Seal coat rolling in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
6.27-10-2016Km 3+550PC work in progressBaru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
7.27-10-2016Km 3+600PC workBaru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
8.27-10-2016Km 3+580PC work in progressBaru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
9.25-10-20163+800Premix CarpetBaru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
10.25-10-2016Km 3+750Site Visit SE sir EE sir and RE sirBaru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
11.25-10-2016Km 3+100Mix roll and Bitumen at Garh Dewal motor roadBaru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
12.19-10-20163/4machinery &material for PC work arranged at sitePraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
13.18-10-20162+800Sieve analysis for wbm g-3Baru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
14.18-10-2016Km 2+810Sieve analysis for WBM G-3Baru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
15.06-10-2016Km 3+450Checking of Width for WBM G-3Baru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
16.28-09-2016Km 3+630Sieve analysis for WBM G-3Baru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
17.25-09-20160+100AIV TEST result found satisfactoryPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
18.25-09-2016site lab at ch 0+100AIV test of 20mm aggregatePraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
19.25-09-20163+770sieve analyses for G 2 aggrigate found okPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
20.25-09-20161+120G3layer material collection in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic