UDRP/PWD/01/34/RD/075
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
86 |
Package Name: |
UDRP/PWD/01/34/RD/075 |
Sanction Cost: |
339.22 lakhs |
District: |
Uttarkashi |
Block: |
Naugaon |
Constituency: |
Purola |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 3135 Gadh-Dewal molthat motor road (3.850 KM.) (completed) |
|
Procurement: |
Package No.: 86
Package Name: UDRP/PWD/01/34/RD/075
Tender Date: 29-12-2014
Current Status: Agreement signed
Achieved on Date: 04-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/34/RD/075
Contractor Name: People Concern Towards Social Realities
|
Start Date: 11-06-2015
Intended Completion Date: 31-01-2017
Original End Date: 10-09-2016
|
Total Bond Cost: 30060931.63 (300.61 lakhs)
Variation Cost: 1206824.25 (12.07 lakhs) Hence Total Bond Cost is 31267755.88 (312.68 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 420840 for 28 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 3.85 KM | 12.99 | 3.85 KM | 3.85 KM | 4.52 | 12.99 | 2. | R/Wall, B/ Wall Type Protection works | 2075.00 m | 118.96 | 2075.00 m | 2075.00 m | 41.4 | 118.96 | 3. | GSB/RBI/G-1 | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 | 4. | G-2 | 3.85 KM | 38.66 | 3.85 KM | 3.85 KM | 13.46 | 38.66 | 5. | G-3 | 3.85 KM | 27.29 | 3.85 KM | 3.85 KM | 9.5 | 27.29 | 6. | PC/CC i/c Prime Coat, Tack Coat | 3.85 KM | 45.78 | 3.85 KM | 3.85 KM | 15.93 | 45.78 | 7. | Culverts/Scupper | 16.00 No | 36.56 | 16.00 No | 16.00 No | 12.72 | 36.56 | 8. | longitudinal Drain | 3800.00 m | 6.46 | 3800.00 m | 3800.00 m | 2.25 | 6.46 | 9. | Crash Barrier | 0.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 10. | Parapet | 0.00 No | 0.00 | 0.00 No | 0.00 No | 0 | 0.00 | 11. | Road Furniture | 13.00 No | 0.62 | 13.00 No | 13.00 No | 0.22 | 0.62 |
Total Amount: |
287.32 |
|
100 |
287.32 |
|
Remarks:
No Remarks
Work Program Made On:
11-08-2015
Updation of work program on:
20-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 17-September-2015 | 17.00 lakhs |
2. | 30-September-2015 | 35.63 lakhs |
3. | 21-January-2016 | 35.89 lakhs |
4. | 06-February-2016 | 0.06 lakhs |
5. | 26-February-2016 | 11.58 lakhs |
6. | 30-March-2016 | 38.78 lakhs |
7. | 26-May-2016 | 16.19 lakhs |
8. | 07-September-2016 | 23.63 lakhs |
9. | 10-October-2016 | 20.73 lakhs |
10. | 31-December-2016 | 54.06 lakhs |
11. | 11-January-2017 | 14.20 lakhs |
12. | 10-April-2017 | 15.24 lakhs |
13. | 18-May-2017 | 9.69 lakhs |
14. | 17-June-2017 | 13.62 lakhs |
15. | 08-December-2017 | 13.28 lakhs |
16. | 13-March-2018 | -8.09 lakhs |
Total |
311.49 lakhs |
% Payment |
99.62 % |
|
Advance Amount: 121.93 lakhs
Recovered Amount: 121.97 lakhs
Balance to be Recovered -0.04 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 218 |
Number of Notice(s) issued: 116 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 05-05-2017 | Ch 1+500 | Track route for Village | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
2. | 05-05-2017 | Ch- 0+300 | Painted Parapet. | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
3. | 01-01-2017 | 3+300 | Discussion regarding site issues with villagers at Garh dewal | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
4. | 01-12-2016 | 1+600 | PC thickness found OK | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
5. | 01-12-2016 | 1+625 | Seal coat rolling in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
6. | 27-10-2016 | Km 3+550 | PC work in progress | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkahsi | See Pic |
7. | 27-10-2016 | Km 3+600 | PC work | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkahsi | See Pic |
8. | 27-10-2016 | Km 3+580 | PC work in progress | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkahsi | See Pic |
9. | 25-10-2016 | 3+800 | Premix Carpet | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkahsi | See Pic |
10. | 25-10-2016 | Km 3+750 | Site Visit SE sir EE sir and RE sir | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkahsi | See Pic |
11. | 25-10-2016 | Km 3+100 | Mix roll and Bitumen at Garh Dewal motor road | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkahsi | See Pic |
12. | 19-10-2016 | 3/4 | machinery &material for PC work arranged at site | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
13. | 18-10-2016 | 2+800 | Sieve analysis for wbm g-3 | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkahsi | See Pic |
14. | 18-10-2016 | Km 2+810 | Sieve analysis for WBM G-3 | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkahsi | See Pic |
15. | 06-10-2016 | Km 3+450 | Checking of Width for WBM G-3 | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkahsi | See Pic |
16. | 28-09-2016 | Km 3+630 | Sieve analysis for WBM G-3 | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkahsi | See Pic |
17. | 25-09-2016 | 0+100 | AIV TEST result found satisfactory | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
18. | 25-09-2016 | site lab at ch 0+100 | AIV test of 20mm aggregate | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
19. | 25-09-2016 | 3+770 | sieve analyses for G 2 aggrigate found ok | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
20. | 25-09-2016 | 1+120 | G3layer material collection in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
|
|