Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/01/33/RD/074 Agreement signed
Project: UDRP-RB Package No.: 85 Package Name: UDRP/PWD/01/33/RD/074 Sanction Cost: 235.23  lakhs
District: Uttarkashi Block: Mori Constituency: Purola Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  3121   Bhadrasu Ramalgaon Motor Road (2.770 KM.) (completed)
Procurement:
Package No.: 85        Package Name: UDRP/PWD/01/33/RD/074        Tender Date: 29-12-2014        Current Status: Agreement signed        Achieved on Date: 18-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/33/RD/074        Contractor Name: Devendra Construction       
Start Date: 24-06-2015        Intended Completion Date: 07-01-2017        Original End Date:  23-09-2016
Total Bond Cost: 19635953.97 (196.36 lakhs)        Variation Cost: 2714236.82 (27.14 lakhs)     Hence Total Bond Cost is   22350190.79 (223.5 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 765804 for 78 days        LD Analysis for Milestone2: calculated LD is Rs 1119252 for 114 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence2.80 KM14.682.80 KM2.80 KM7.8514.68
2.R/Wall, B/ Wall Type Protection works1693.00 m59.601693.00 m1693.00 m31.8859.60
3.GSB/RBI/G-10.00 KM0.000.00 KM0.00 KM00.00
4.G-22.80 KM26.522.80 KM2.80 KM14.1826.52
5.G-32.80 KM16.542.80 KM2.80 KM8.8516.54
6.PC/CC i/c Prime Coat, Tack Coat2.80 KM33.362.80 KM2.80 KM17.8433.36
7.Cause Way1.00 No2.871.00 No1.00 No1.542.87
8.Culverts/Scupper 10.00 No23.6411.00 No11.00 No12.6423.64
9.longitudinal Drain2700.00 m5.442700.00 m2700.00 m2.915.44
10.Crash Barrier40.00 m0.7740.00 m40.00 m0.410.77
11.Parapet200.00 No2.63200.00 No200.00 No1.412.63
12.Road Furniture13.00 No0.9213.00 No13.00 No0.490.92
Total Amount: 186.97 100   186.97
Remarks: No Remarks       Work Program Made On: 11-08-2015       Updation of work program on: 03-08-2016      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-September-201511.00  lakhs
2.30-September-20154.25  lakhs
3.26-October-20156.82  lakhs
4.21-January-201613.16  lakhs
5.06-February-20160.06  lakhs
6.19-February-201616.62  lakhs
7.30-March-201614.86  lakhs
8.11-May-201619.93  lakhs
9.10-August-20167.32  lakhs
10.29-September-201636.70  lakhs
11.27-October-201610.20  lakhs
12.15-December-201629.62  lakhs
13.25-February-201720.97  lakhs
14.31-July-201721.56  lakhs
15.28-August-20179.85  lakhs
Total 222.92  lakhs
% Payment 99.74 %
Advance Amount:  95.72  lakhs        Recovered Amount:  95.72  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 202     No. of Test Done : 247      No. of Test Passed : 222      No. of Test Failed : 25   Test report of this package
Number of Pics Available on Web Repository: 257
Number of Notice(s) issued: 97

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-01-20170+300Protection work in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
2.01-01-20171+175Site visit regarding quality & progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
3.30-12-20162. 350Retaining wall work in progressAshish AnthwalEnvironment SpecialistPIU UDRP R&B Dehradun See Pic
4.27-12-20160. 400Retaining wall dry in progressAshish AnthwalEnvironment SpecialistPIU UDRP R&B Dehradun See Pic
5.20-12-20162400P .c work rollling on progresssPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
6.01-12-20160/0PC work completed patri dressing and proper compaction required contractor instructed to doPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
7.16-11-20162400P.c workPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
8.08-11-20160+100P .c work ....bhadrashu ramalgounPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
9.08-11-2016350H.p bend countune. slaidingPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
10.30-10-20161+650PC thickness found 25mm during inspection by SE sirPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
11.18-10-20162+000PC laying in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
12.18-10-20162+575WBM laying G2 in progress 2500 to 2700Praveen GuptaREDSC1 R&B WB Uttarkashi See Pic
13.18-10-20162+600G2 layer work in progress from 2500 to 2700Praveen GuptaREDSC1 R&B WB Uttarkashi See Pic
14.15-10-2016P.c work badrasu M/RP.C work badrasu M/RPrateek TalwarJEUDRP R&B Uttarkashi See Pic
15.14-10-2016P.c work badrasu M/RP.C work badrasu M/RPrateek TalwarJEUDRP R&B Uttarkashi See Pic
16.13-10-20162+400Cleaning for PC work in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
17.09-10-20162275 to 2300thikness checkingPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
18.09-10-20162350compaction chacking ...thicknessPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
19.09-10-20162400cleening suface for pc .....Praveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
20.09-10-20162500k.c drain ....vertical portionPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic