UDRP/PWD/01/33/RD/073 Agreement signed
Project: UDRP-RB Package No.: 84 Package Name: UDRP/PWD/01/33/RD/073 Sanction Cost: 669.46  lakhs
District: Uttarkashi Block: Mori Constituency: Purola Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  3118   Barnali Jhotari Motor Road (9.050 KM.) (completed)
Procurement:
Package No.: 84        Package Name: UDRP/PWD/01/33/RD/073        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 03-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/33/RD/073        Contractor Name: Dinesh Prasad Dangwal       
Start Date: 10-10-2015        Intended Completion Date: 23-03-2017        Original End Date:  09-01-2017
Total Bond Cost: 61277047.15 (612.77 lakhs)        Variation Cost: 4931535.87 (49.32 lakhs)     Hence Total Bond Cost is   66208583.02 (662.09 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 337029 for 11 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence9.00 KM27.009.00 KM9.00 KM4.7127.00
2.R/Wall, B/ Wall Type Protection works2616.00 m256.812616.00 m2616.00 m44.76256.81
3.G-23.30 KM12.503.30 KM3.30 KM2.1812.50
4.G-33.30 KM27.873.30 KM3.30 KM4.8627.87
5.PC/CC i/c Prime Coat, Tack Coat9.00 KM92.949.00 KM9.00 KM16.292.94
6.Culverts/Scupper 24.00 No72.2324.00 No24.00 No12.5972.23
7.longitudinal Drain9000.00 m82.829000.00 m9000.00 m14.4382.82
8.Crash Barrier0.00 m0.000.00 m0.00 m00.00
9.Road Furniture77.00 No1.6277.00 No77.00 No0.281.62
Total Amount: 573.79 100   573.79
Remarks: No Remarks       Work Program Made On: 29-10-2015       Updation of work program on: 16-03-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.18-January-201645.74  lakhs
2.19-February-201629.06  lakhs
3.17-March-201633.95  lakhs
4.30-March-201642.15  lakhs
5.09-June-201676.08  lakhs
6.29-June-201631.89  lakhs
7.09-August-201672.58  lakhs
8.24-September-201663.87  lakhs
9.26-October-201640.82  lakhs
10.15-December-2016128.29  lakhs
11.31-January-201716.64  lakhs
12.30-March-201773.69  lakhs
13.31-May-20187.53  lakhs
Total 662.29  lakhs
% Payment 100.03 %
Advance Amount:  75.82  lakhs        Recovered Amount:  75.82  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 310     No. of Test Done : 378      No. of Test Passed : 369      No. of Test Failed : 9   Test report of this package
Number of Pics Available on Web Repository: 107
Number of Notice(s) issued: 86

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-01-20174+200Parapet work in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
2.01-01-20179+000Site visit regarding quality & progress reviewPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
3.01-12-20160/1PC work completed patri dressing and proper compaction required instructed to doPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
4.06-11-20161800P.c surface ..seal coat is not properPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
5.06-11-2016600P.c work ..barnali jhotari motor roadPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
6.19-10-20166+800PC work in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
7.19-10-20167200seal coat laying in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
8.18-10-20166+625PC compaction in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
9.18-10-20166+675tack coat laying for PC workPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
10.18-10-20166900thickness check p.cPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
11.18-10-20167200temprature ..checking .....p.c workPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
12.18-10-20167900Emulsion use for pkg 73 p.c works ......Praveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
13.18-10-20167900todays ready for p.c at pkg 73 .....pure ....Praveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
14.13-10-20163+700WBM laying in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
15.13-10-20167+800paver for PC work arrived at sitePraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
16.13-10-20168+800G3 layer completedPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
17.13-10-20169kmrollling ..painting .....surface ...Praveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
18.09-10-2016jhotari road last point 9kmdressing surface for last point jhotari motor road .....station pointPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
19.09-10-2016g2 laying worklaying workPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
20.22-09-20163875wbm g2 thicknessPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic