UDRP/PWD/01/31/RD/072
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
83 |
Package Name: |
UDRP/PWD/01/31/RD/072 |
Sanction Cost: |
474.13 lakhs |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 3151 Gagnani Motor Pull to Bhangeli Motor Road (4.600 KM.) (completed) |
|
Procurement: |
Package No.: 83
Package Name: UDRP/PWD/01/31/RD/072
Tender Date: 29-12-2014
Current Status: Agreement signed
Achieved on Date: 04-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/31/RD/072
Contractor Name: Seema Construction Company
|
Start Date: 11-06-2015
Intended Completion Date: 20-06-2017
Original End Date: 10-09-2016
|
Total Bond Cost: 42946810.39 (429.47 lakhs)
Variation Cost: 4223665.86 (42.24 lakhs) Hence Total Bond Cost is 47170476.25 (471.7 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2104354 for 98 days
LD Analysis for Milestone2: calculated LD is Rs 4509330 for 210 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 4.60 KM | 32.64 | 4.60 KM | 4.60 KM | 7.45 | 32.64 | 2. | R/Wall, B/ Wall Type Protection works | 2965.00 m | 158.28 | 2965.00 m | 2965.00 m | 36.13 | 158.28 | 3. | G-2 | 4.60 KM | 63.86 | 4.60 KM | 4.60 KM | 14.58 | 63.86 | 4. | G-3 | 4.60 KM | 33.96 | 4.60 KM | 4.60 KM | 7.75 | 33.96 | 5. | PC/CC i/c Prime Coat, Tack Coat | 4.60 KM | 57.11 | 4.60 KM | 4.60 KM | 13.04 | 57.11 | 6. | Cause Way | 1.00 No | 34.65 | 1.00 No | 1.00 No | 7.91 | 34.65 | 7. | Culverts/Scupper | 7.00 No | 30.96 | 7.00 No | 7.00 No | 7.07 | 30.96 | 8. | longitudinal Drain | 2500.00 m | 13.15 | 2500.00 m | 2500.00 m | 3 | 13.15 | 9. | Crash Barrier | 200.00 m | 0.48 | 200.00 m | 200.00 m | 0.11 | 0.48 | 10. | Parapet | 267.00 No | 11.78 | 267.00 No | 267.00 No | 2.69 | 11.78 | 11. | Road Furniture | 39.00 No | 1.20 | 39.00 No | 39.00 No | 0.27 | 1.20 |
Total Amount: |
438.07 |
|
100 |
438.07 |
|
Remarks:
No Remarks
Work Program Made On:
11-08-2015
Updation of work program on:
30-06-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-September-2015 | 12.00 lakhs |
2. | 30-September-2015 | 8.24 lakhs |
3. | 19-December-2015 | 0.03 lakhs |
4. | 21-January-2016 | 29.59 lakhs |
5. | 19-February-2016 | 39.76 lakhs |
6. | 30-March-2016 | 10.06 lakhs |
7. | 25-April-2016 | 24.92 lakhs |
8. | 13-July-2016 | 40.18 lakhs |
9. | 26-October-2016 | 45.30 lakhs |
10. | 31-January-2017 | 37.41 lakhs |
11. | 18-May-2017 | 35.73 lakhs |
12. | 20-May-2017 | 21.38 lakhs |
13. | 30-June-2017 | 80.92 lakhs |
14. | 12-October-2017 | 17.21 lakhs |
15. | 13-October-2017 | 14.40 lakhs |
16. | 23-December-2017 | 25.75 lakhs |
17. | 31-January-2018 | 17.62 lakhs |
18. | 31-May-2018 | 10.57 lakhs |
Total |
471.07 lakhs |
% Payment |
99.87 % |
|
Advance Amount: 96.82 lakhs
Recovered Amount: 96.82 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 154 |
Number of Notice(s) issued: 117 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-09-2017 | Ch 1/30 | Road Damaged due to sinking | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
2. | 28-09-2017 | Ch 3/20 | Slip at 3/20 | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
3. | 30-08-2017 | Ch. 2/10 | Thickness Checking of PC found 22mm ok | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
4. | 07-05-2017 | Ch 4/17 | P.c work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
5. | 21-04-2017 | Ch 3/18 | SE world bank tehri visit | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
6. | 23-01-2017 | 4/13 | Weep hole not found ,slop not proper in KC drain instructed to rectify the work | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
7. | 31-12-2016 | WBM G 2 km 1/18 | WBM G 2 work in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
8. | 21-12-2016 | Ch 4/6 | Crust checking | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
9. | 12-12-2016 | WBM G. 3 KM 1/1 to 1/4 | WBM G. 3 | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
10. | 12-12-2016 | WBM G.3 km 1/3 | WBM G.3 | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
11. | 01-12-2016 | 1/20 | G2 grading stone collection in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
12. | 24-11-2016 | WBM G. 2 km 1/21 | WBM G. 2 | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
13. | 14-10-2016 | Site visit SE SIR | SE SIR site visit | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
14. | 13-10-2016 | 0/35 | inspection of sinking portion during site visit by SE New Tehri | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
15. | 13-10-2016 | 4/18 | WBM gradation test on site found oversized rejected from 4/15 to 4/24 | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
16. | 05-10-2016 | Ch 0/6 | Damages during monsoon | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
17. | 05-10-2016 | WBM G.3 km 4/10 | WBM G.3 | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
18. | 05-10-2016 | Aiv testing km.4/11 | Aiv testing | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
19. | 29-09-2016 | 4/2 | profile correction work in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
20. | 29-09-2016 | 4/18 | G3 laying in progress material not found well graded instructed to rectify | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
|
|