Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/01/31/RD/071 Agreement signed
Project: UDRP-RB Package No.: 82 Package Name: UDRP/PWD/01/31/RD/071 Sanction Cost: 666.80  lakhs
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 2
Subproject in this package
1  3123   Bhatwari-Barsu Motor Road (2.250 KM.) (completed)
2  3130   Chadethi-Raitha Motor Road (2.030 KM.) (completed)
Procurement:
Package No.: 82        Package Name: UDRP/PWD/01/31/RD/071        Tender Date: 11-09-2015        Current Status: Agreement signed        Achieved on Date: 20-02-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/31/RD/071        Contractor Name: Parth Construction       
Start Date: 27-02-2016        Intended Completion Date: 28-02-2018        Original End Date:  26-12-2016
Total Bond Cost: 35940985.37 (359.41 lakhs)        Variation Cost: 29465244.98 (294.65 lakhs)     Hence Total Bond Cost is   65406230.35 (654.06 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2282190 for 127 days        LD Analysis for Milestone2: calculated LD is Rs 3899490 for 217 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence4.35 KM27.754.35 KM4.35 KM5.2727.75
2.R/Wall, B/ Wall Type Protection works1789.00 m294.921789.00 m1789.00 m54.2294.92
3.G-21.65 KM31.011.65 KM1.65 KM5.7431.01
4.G-32.50 KM19.232.50 KM2.50 KM3.6319.23
5.PC/CC i/c Prime Coat, Tack Coat4.35 KM53.384.35 KM4.35 KM9.8753.38
6.Culverts/Scupper 6.00 No20.986.00 No6.00 No4.0520.98
7.longitudinal Drain3550.00 m78.243550.00 m3550.00 m14.2978.24
8.Crash Barrier0.00 m0.000.00 m0.00 m00.00
9.Parapet500.00 No13.50500.00 No500.00 No2.5513.50
10.Road Furniture56.00 No2.1556.00 No56.00 No0.42.15
Total Amount: 541.16 100   541.16
Remarks: No Remarks       Work Program Made On: 18-05-2016       Updation of work program on: 28-03-2018      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.22-July-201636.89  lakhs
2.14-September-201610.25  lakhs
3.14-October-201626.62  lakhs
4.16-December-201621.94  lakhs
5.02-March-201754.73  lakhs
6.17-June-201762.77  lakhs
7.31-July-201724.84  lakhs
8.29-August-201714.90  lakhs
9.13-October-201741.28  lakhs
10.20-November-201715.38  lakhs
11.27-November-201751.05  lakhs
12.23-December-20172.26  lakhs
13.15-January-201856.51  lakhs
14.17-February-20188.90  lakhs
15.26-July-201836.39  lakhs
16.29-September-2018110.74  lakhs
17.26-March-201831.02  lakhs
18.31-May-201849.50  lakhs
Total 655.97  lakhs
% Payment 100.29 %
Advance Amount:  12.06  lakhs        Recovered Amount:  12.06  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 315     No. of Test Done : 588      No. of Test Passed : 561      No. of Test Failed : 27   Test report of this package
Number of Pics Available on Web Repository: 191
Number of Notice(s) issued: 102

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-12-2017Ch 1725Debris disposalRamesh ChandEEUDRP R&B Uttarkashi See Pic
2.05-12-2017Ch 0.600Using zycotherm for PC workNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
3.25-11-2017Ch 1.875PC thickness checkingNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
4.24-11-2017Ch0+800WBM G2 layer water curing on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
5.24-11-2017Ch1+675R/wall work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
6.24-11-2017Ch1+870Premix carpet layer thickness checkingNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
7.24-11-2017Km2Premix carpet laying work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
8.16-11-2017Ch 0/1P.C work in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
9.05-11-2017Ch 0.200Checking ofNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
10.05-11-2017Ch 1.400Plum concrete work in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
11.02-11-2017C0+450Site cleaning work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
12.02-11-2017Ch0+310Water sprinkle at wbm g2 layerNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
13.02-11-2017Ch0+250Wbm g2 layer thickness checkingNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
14.02-11-2017Ch0+200Wbm g2 rolling work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
15.02-11-2017Ch0/100Site inspaction by SE sirNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
16.02-11-2017Ch0+290Wbm g2 layer thickness checkingNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
17.02-11-2017Ch0+300Wbm g2 layer water sprinkleNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
18.02-11-2017Ch0+325Site cleaning work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
19.02-11-2017Ch1+400Site inspaction by SE sirNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
20.02-11-2017Ch1+300Local problem discussionNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic