UDRP/PWD/01/31/RD/071
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
82 |
Package Name: |
UDRP/PWD/01/31/RD/071 |
Sanction Cost: |
666.80 lakhs |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 3123 Bhatwari-Barsu Motor Road (2.250 KM.) (completed) | 2 3130 Chadethi-Raitha Motor Road (2.030 KM.) (completed) |
|
Procurement: |
Package No.: 82
Package Name: UDRP/PWD/01/31/RD/071
Tender Date: 11-09-2015
Current Status: Agreement signed
Achieved on Date: 20-02-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/31/RD/071
Contractor Name: Parth Construction
|
Start Date: 27-02-2016
Intended Completion Date: 28-02-2018
Original End Date: 26-12-2016
|
Total Bond Cost: 35940985.37 (359.41 lakhs)
Variation Cost: 29465244.98 (294.65 lakhs) Hence Total Bond Cost is 65406230.35 (654.06 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2282190 for 127 days
LD Analysis for Milestone2: calculated LD is Rs 3899490 for 217 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 4.35 KM | 27.75 | 4.35 KM | 4.35 KM | 5.27 | 27.75 | 2. | R/Wall, B/ Wall Type Protection works | 1789.00 m | 294.92 | 1789.00 m | 1789.00 m | 54.2 | 294.92 | 3. | G-2 | 1.65 KM | 31.01 | 1.65 KM | 1.65 KM | 5.74 | 31.01 | 4. | G-3 | 2.50 KM | 19.23 | 2.50 KM | 2.50 KM | 3.63 | 19.23 | 5. | PC/CC i/c Prime Coat, Tack Coat | 4.35 KM | 53.38 | 4.35 KM | 4.35 KM | 9.87 | 53.38 | 6. | Culverts/Scupper | 6.00 No | 20.98 | 6.00 No | 6.00 No | 4.05 | 20.98 | 7. | longitudinal Drain | 3550.00 m | 78.24 | 3550.00 m | 3550.00 m | 14.29 | 78.24 | 8. | Crash Barrier | 0.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 9. | Parapet | 500.00 No | 13.50 | 500.00 No | 500.00 No | 2.55 | 13.50 | 10. | Road Furniture | 56.00 No | 2.15 | 56.00 No | 56.00 No | 0.4 | 2.15 |
Total Amount: |
541.16 |
|
100 |
541.16 |
|
Remarks:
No Remarks
Work Program Made On:
18-05-2016
Updation of work program on:
28-03-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 22-July-2016 | 36.89 lakhs |
2. | 14-September-2016 | 10.25 lakhs |
3. | 14-October-2016 | 26.62 lakhs |
4. | 16-December-2016 | 21.94 lakhs |
5. | 02-March-2017 | 54.73 lakhs |
6. | 17-June-2017 | 62.77 lakhs |
7. | 31-July-2017 | 24.84 lakhs |
8. | 29-August-2017 | 14.90 lakhs |
9. | 13-October-2017 | 41.28 lakhs |
10. | 20-November-2017 | 15.38 lakhs |
11. | 27-November-2017 | 51.05 lakhs |
12. | 23-December-2017 | 2.26 lakhs |
13. | 15-January-2018 | 56.51 lakhs |
14. | 17-February-2018 | 8.90 lakhs |
15. | 26-July-2018 | 36.39 lakhs |
16. | 29-September-2018 | 110.74 lakhs |
17. | 26-March-2018 | 31.02 lakhs |
18. | 31-May-2018 | 49.50 lakhs |
Total |
655.97 lakhs |
% Payment |
100.29 % |
|
Advance Amount: 12.06 lakhs
Recovered Amount: 12.06 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 191 |
Number of Notice(s) issued: 102 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-12-2017 | Ch 1725 | Debris disposal | Ramesh Chand | EE | UDRP R&B Uttarkashi | See Pic |
2. | 05-12-2017 | Ch 0.600 | Using zycotherm for PC work | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
3. | 25-11-2017 | Ch 1.875 | PC thickness checking | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
4. | 24-11-2017 | Ch0+800 | WBM G2 layer water curing on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
5. | 24-11-2017 | Ch1+675 | R/wall work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
6. | 24-11-2017 | Ch1+870 | Premix carpet layer thickness checking | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
7. | 24-11-2017 | Km2 | Premix carpet laying work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
8. | 16-11-2017 | Ch 0/1 | P.C work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
9. | 05-11-2017 | Ch 0.200 | Checking of | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
10. | 05-11-2017 | Ch 1.400 | Plum concrete work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
11. | 02-11-2017 | C0+450 | Site cleaning work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
12. | 02-11-2017 | Ch0+310 | Water sprinkle at wbm g2 layer | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
13. | 02-11-2017 | Ch0+250 | Wbm g2 layer thickness checking | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
14. | 02-11-2017 | Ch0+200 | Wbm g2 rolling work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
15. | 02-11-2017 | Ch0/100 | Site inspaction by SE sir | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
16. | 02-11-2017 | Ch0+290 | Wbm g2 layer thickness checking | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
17. | 02-11-2017 | Ch0+300 | Wbm g2 layer water sprinkle | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
18. | 02-11-2017 | Ch0+325 | Site cleaning work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
19. | 02-11-2017 | Ch1+400 | Site inspaction by SE sir | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
20. | 02-11-2017 | Ch1+300 | Local problem discussion | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
|
|