UDRP/PWD/06/71/RD/069
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
80 |
Package Name: |
UDRP/PWD/06/71/RD/069 |
Sanction Cost: |
706.60 lakhs |
District: |
Pauri |
Block: |
Dogadda |
Constituency: |
Yamkeshwar |
Circle: |
|
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 2275 Nathukhal Pokhrikhet MR (7.000 KM.) (completed) | 2 2276 Kasyali Khobra MR (8.000 KM.) (completed) |
|
Procurement: |
Package No.: 80
Package Name: UDRP/PWD/06/71/RD/069
Tender Date: 28-01-2015
Current Status: Agreement signed
Achieved on Date: 16-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/71/RD/069
Contractor Name: Balwinder Singh and Co.
|
Start Date: 22-06-2015
Intended Completion Date: 31-10-2018
Original End Date: 21-09-2016
|
Total Bond Cost: 64590492.74 (645.9 lakhs)
Variation Cost: -3468998.15 (-34.69 lakhs) Hence Total Bond Cost is 61121494.59 (611.21 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 10366695 for 321 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 4.42 KM | 39.98 | 4.42 KM | 4.42 KM | 6.21 | 39.98 | 2. | R/Wall, B/ Wall Type Protection works | 1641.00 m | 171.37 | 1641.00 m | 1641.00 m | 27.27 | 171.37 | 3. | GSB/RBI/G-1 | 7.33 KM | 49.66 | 7.33 KM | 7.33 KM | 9.44 | 49.66 | 4. | G-2 | 7.96 KM | 36.81 | 7.96 KM | 7.96 KM | 6.94 | 36.81 | 5. | G-3 | 10.83 KM | 43.47 | 10.83 KM | 10.83 KM | 7.9 | 43.47 | 6. | PC/CC i/c Prime Coat, Tack Coat | 14.63 KM | 137.78 | 14.63 KM | 14.63 KM | 21.9 | 137.78 | 7. | Cause Way | 2.00 No | 4.62 | 2.00 No | 2.00 No | 0.88 | 4.62 | 8. | Culverts/Scupper | 40.00 No | 69.28 | 40.00 No | 40.00 No | 10.73 | 69.28 | 9. | longitudinal Drain | 11050.00 m | 12.58 | 11050.00 m | 11050.00 m | 2.02 | 12.58 | 10. | Crash Barrier | 208.00 m | 4.63 | 208.00 m | 208.00 m | 0.72 | 4.63 | 11. | Parapet | 143.00 No | 2.99 | 143.00 No | 143.00 No | 0.46 | 2.99 | 12. | Road Furniture | 210.00 No | 4.08 | 210.00 No | 210.00 No | 0.62 | 4.08 | 13. | Other Allied Works & Finishing Work | 2.00 Job | 28.49 | 2.00 Job | 2.00 Job | 4.9 | 28.49 |
Total Amount: |
605.74 |
|
100 |
605.74 |
|
Remarks:
No Remarks
Work Program Made On:
05-10-2015
Updation of work program on:
08-04-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-September-2015 | 103.89 lakhs |
2. | 31-December-2015 | 54.33 lakhs |
3. | 05-May-2016 | 44.73 lakhs |
4. | 21-June-2016 | 27.89 lakhs |
5. | 31-December-2016 | 20.31 lakhs |
6. | 27-March-2017 | 33.15 lakhs |
7. | 30-June-2017 | 56.20 lakhs |
8. | 29-May-2018 | 51.96 lakhs |
9. | 14-August-2018 | 95.49 lakhs |
10. | 28-February-2019 | 72.33 lakhs |
11. | 30-April-2019 | 7.90 lakhs |
12. | 18-June-2019 | 0.17 lakhs |
13. | 09-July-2019 | 9.45 lakhs |
14. | 31-January-2016 | 23.57 lakhs |
15. | 04-May-2016 | 21.94 lakhs |
Total |
623.31 lakhs |
% Payment |
101.98 % |
|
Advance Amount: 79.88 lakhs
Recovered Amount: 79.88 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 78 |
Number of Notice(s) issued: 146 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 18-08-2018 | Ch 7+290 | SRMD R/wall damage | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
2. | 18-08-2018 | Ch 10/27 | SRMD R/wall damage | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
3. | 18-08-2018 | Ch 10/34 | SRMD Slip | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
4. | 18-08-2018 | Ch 13/4 | SRMD Slip | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
5. | 18-08-2018 | Ch. 6/7 | SRMD Slip and road is close | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
6. | 18-08-2018 | Ch 4/10 | SRMD slip | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
7. | 18-08-2018 | Ch 4/10 | SRMD R/Wall damage | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
8. | 18-08-2018 | Ch 2/28 | SRMD R/Wall damage | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
9. | 19-05-2018 | 11+150 | Rolling of PC in progress | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
10. | 08-05-2018 | Ch. 8/25 | Laying and compaction of PC | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
11. | 08-05-2018 | Ch. 8/25 | Checking tempeature of PC during laying | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
12. | 08-05-2018 | Site lab | Bitumin extraction test | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
13. | 04-05-2018 | Ch 1/6 | P.C work is in progress | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
14. | 04-05-2018 | Ch 1/5 | Prime coated surface | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
15. | 04-05-2018 | Ch 1/12 | Compacted PC surafce | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
16. | 23-04-2018 | Ch 0/35 | Laying of PC | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
17. | 23-04-2018 | Ch 0/35 | Checking tempeature of PC before laying | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
18. | 23-04-2018 | Ch 0/38 | Prime coated surface | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
19. | 15-12-2017 | Km 4 | Visit by S.E (PIU) sir | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
20. | 15-12-2017 | Km 14 | S.E sir (PIU) visit | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
|
|