Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/06/71/RD/069 Agreement signed
Project: UDRP-RB Package No.: 80 Package Name: UDRP/PWD/06/71/RD/069 Sanction Cost: 706.60  lakhs
District: Pauri Block: Dogadda Constituency: Yamkeshwar Circle:
DEA: DEA Pauri DSC: Egis International DSC Scope: Design and Supervision No.of Sub project : 2
Subproject in this package
1  2275   Nathukhal Pokhrikhet MR (7.000 KM.) (completed)
2  2276   Kasyali Khobra MR (8.000 KM.) (completed)
Procurement:
Package No.: 80        Package Name: UDRP/PWD/06/71/RD/069        Tender Date: 28-01-2015        Current Status: Agreement signed        Achieved on Date: 16-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/71/RD/069        Contractor Name: Balwinder Singh and Co.       
Start Date: 22-06-2015        Intended Completion Date: 31-10-2018        Original End Date:  21-09-2016
Total Bond Cost: 64590492.74 (645.9 lakhs)        Variation Cost: -3468998.15 (-34.69 lakhs)     Hence Total Bond Cost is   61121494.59 (611.21 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 10366695 for 321 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence4.42 KM39.984.42 KM4.42 KM6.2139.98
2.R/Wall, B/ Wall Type Protection works1641.00 m171.371641.00 m1641.00 m27.27171.37
3.GSB/RBI/G-17.33 KM49.667.33 KM7.33 KM9.4449.66
4.G-27.96 KM36.817.96 KM7.96 KM6.9436.81
5.G-310.83 KM43.4710.83 KM10.83 KM7.943.47
6.PC/CC i/c Prime Coat, Tack Coat14.63 KM137.7814.63 KM14.63 KM21.9137.78
7.Cause Way2.00 No4.622.00 No2.00 No0.884.62
8.Culverts/Scupper 40.00 No69.2840.00 No40.00 No10.7369.28
9.longitudinal Drain11050.00 m12.5811050.00 m11050.00 m2.0212.58
10.Crash Barrier208.00 m4.63208.00 m208.00 m0.724.63
11.Parapet143.00 No2.99143.00 No143.00 No0.462.99
12.Road Furniture210.00 No4.08210.00 No210.00 No0.624.08
13.Other Allied Works & Finishing Work 2.00 Job28.492.00 Job2.00 Job4.928.49
Total Amount: 605.74 100   605.74
Remarks: No Remarks       Work Program Made On: 05-10-2015       Updation of work program on: 08-04-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-September-2015103.89  lakhs
2.31-December-201554.33  lakhs
3.05-May-201644.73  lakhs
4.21-June-201627.89  lakhs
5.31-December-201620.31  lakhs
6.27-March-201733.15  lakhs
7.30-June-201756.20  lakhs
8.29-May-201851.96  lakhs
9.14-August-201895.49  lakhs
10.28-February-201972.33  lakhs
11.30-April-20197.90  lakhs
12.18-June-20190.17  lakhs
13.09-July-20199.45  lakhs
14.31-January-201623.57  lakhs
15.04-May-201621.94  lakhs
Total 623.31  lakhs
% Payment 101.98 %
Advance Amount:  79.88  lakhs        Recovered Amount:  79.88  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 420     No. of Test Done : 441      No. of Test Passed : 422      No. of Test Failed : 19   Test report of this package
Number of Pics Available on Web Repository: 78
Number of Notice(s) issued: 146

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.18-08-2018Ch 7+290SRMD R/wall damageAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
2.18-08-2018Ch 10/27SRMD R/wall damageAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
3.18-08-2018Ch 10/34SRMD SlipAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
4.18-08-2018Ch 13/4SRMD SlipAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
5.18-08-2018Ch. 6/7SRMD Slip and road is closeAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
6.18-08-2018Ch 4/10SRMD slipAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
7.18-08-2018Ch 4/10SRMD R/Wall damageAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
8.18-08-2018Ch 2/28SRMD R/Wall damageAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
9.19-05-201811+150Rolling of PC in progressManoj BhattREDSC2 R&B WB Pauri See Pic
10.08-05-2018Ch. 8/25Laying and compaction of PCAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
11.08-05-2018Ch. 8/25Checking tempeature of PC during layingAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
12.08-05-2018Site labBitumin extraction testAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
13.04-05-2018Ch 1/6P.C work is in progressAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
14.04-05-2018Ch 1/5Prime coated surfaceAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
15.04-05-2018Ch 1/12Compacted PC surafceAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
16.23-04-2018Ch 0/35Laying of PCAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
17.23-04-2018Ch 0/35Checking tempeature of PC before layingAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
18.23-04-2018Ch 0/38Prime coated surfaceAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
19.15-12-2017Km 4Visit by S.E (PIU) sirAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
20.15-12-2017Km 14S.E sir (PIU) visitAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic