Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/01/32/RD/008 Agreement signed
Project: UDRP-RB Package No.: 8 Package Name: UDRP/PWD/01/32/RD/008 Sanction Cost: 1398.72  lakhs
District: Uttarkashi Block: Chinyalisaur Constituency: Yamunotri Circle: Tehri WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  3101   Chinyalisaur-Jogath Motor road (20.000 KM.) (completed)
Procurement:
Package No.: 8        Package Name: UDRP/PWD/01/32/RD/008        Tender Date: 14-08-2014        Current Status: Agreement signed        Achieved on Date: 19-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/32/RD/008        Contractor Name: Bharat Construction       
Start Date: 27-02-2015        Intended Completion Date: 10-12-2017        Original End Date:  26-05-2016
Total Bond Cost: 127545587.7 (1275.46 lakhs)        Variation Cost: -12293693.86 (-122.94 lakhs)     Hence Total Bond Cost is   115251893.84 (1152.52 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 13009692 for +204 days        LD Analysis for Milestone2: calculated LD is Rs 15305520 for 240 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.50 KM6.530.50 KM0.50 KM0.526.53
2.R/Wall, B/ Wall Type Protection works1102.00 m136.001102.00 m1102.00 m10.85136.00
3.GSB/RBI/G-10.45 KM1.560.45 KM0.45 KM0.121.56
4.G-20.45 KM2.080.45 KM0.45 KM0.172.08
5.G-31.00 KM3.011.00 KM1.00 KM0.243.01
6.BM i/c Prime Coat, Tack Coat21.40 KM423.0021.40 KM21.40 KM33.73423.00
7.SDBC i/c Tackcoat21.40 KM264.7221.40 KM21.40 KM21.11264.72
8.Cause Way0.00 No0.000.00 No0.00 No00.00
9.Culverts/Scupper 53.00 No115.7553.00 No53.00 No9.23115.75
10.longitudinal Drain20700.00 m109.8320700.00 m20700.00 m8.76109.83
11.Crash Barrier4000.00 m187.664000.00 m4000.00 m14.97187.66
12.Road Furniture219.00 No3.87219.00 No219.00 No0.313.87
Total Amount: 1254.01 100   1254.01
Remarks: No Remarks       Work Program Made On: 31-03-2015       Updation of work program on: 26-05-2018      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-March-201535.53  lakhs
2.18-May-201519.35  lakhs
3.12-June-20158.51  lakhs
4.25-July-201517.88  lakhs
5.09-November-201540.30  lakhs
6.19-January-201636.79  lakhs
7.06-February-20160.03  lakhs
8.30-March-201636.82  lakhs
9.03-July-201640.87  lakhs
10.31-July-2016278.91  lakhs
11.26-October-201620.41  lakhs
12.16-December-2016127.96  lakhs
13.31-March-201797.28  lakhs
14.19-May-201735.14  lakhs
15.13-October-2017154.59  lakhs
16.29-November-201756.12  lakhs
17.08-December-201751.02  lakhs
18.23-December-20172.56  lakhs
19.26-December-201735.00  lakhs
20.17-February-201813.67  lakhs
21.27-February-201820.67  lakhs
22.31-March-201823.09  lakhs
23.28-October-20182.60  lakhs
Total 1155.1  lakhs
% Payment 100.22 %
Advance Amount:  420.93  lakhs        Recovered Amount:  420.93  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1492     No. of Test Done : 1734      No. of Test Passed : 1695      No. of Test Failed : 39   Test report of this package
Number of Pics Available on Web Repository: 683
Number of Notice(s) issued: 185

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.09-03-20187/6CE sir, SE sir, EE sir visit at chinyali jogath MR pkg-008Ankit KuriyalJEUDRP R&B Uttarkashi See Pic
2.25-12-20171/30Visit by World bank missionChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
3.20-12-20171/30Chinyali jogath MR pkg 008 visit by world bank missionAnkit KuriyalJEUDRP R&B Uttarkashi See Pic
4.20-12-20171/24Chinyali jogath MR visit by world bank mission pkg 008Ankit KuriyalJEUDRP R&B Uttarkashi See Pic
5.14-12-20171/24Visit by S E sirChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
6.12-12-2017Chinyali jogat road ch 2/25Retaining wall made for protection in damaged portionRamesh ChandEEUDRP R&B Uttarkashi See Pic
7.07-12-2017Ch3/17WBM G3 layer rolling work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
8.02-12-2017Km5 hot mix plantSdbc mix production on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
9.02-12-2017Km5hmpBitumen tank temperatureNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
10.02-12-20171/750BM mix laying work on progress at chinyali jogath MRNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
11.25-11-201714/10SDBC LAYINGChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
12.18-11-2017Hot mix plant at km 5, chinyali jogath MRSDBC mix production on progress at chinyali jogath MRNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
13.18-11-2017Hot mix plant, km 5, chinyali jogath MRSDBC laying work on progress at chinyali jogath MR /pkg 008Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
14.16-11-2017Ch15/04SDBC work in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
15.13-11-201716/4SDBC Work start today .Chandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
16.10-11-201714/28B.M.. work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
17.09-11-201714/27B.M. work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
18.09-11-2017Km5HMPBM production on progress at chinyali jogath MR, pkg 008Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
19.09-11-2017Km5Hmp plant inspaction by SE SirNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
20.08-11-201714/38B.M. work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic