UDRP/PWD/06/71/RD/067 Agreement signed
Project: UDRP-RB Package No.: 78 Package Name: UDRP/PWD/06/71/RD/067 Sanction Cost: 358.32  lakhs
District: Pauri Block: Yamkeshwar Constituency: Yamkeshwar Circle: Tehri WB Circle
DEA: DEA Pauri DSC: Egis International DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  2218   Neelkanth Link MR (5.000 KM.) (completed)
Procurement:
Package No.: 78        Package Name: UDRP/PWD/06/71/RD/067        Tender Date: 28-01-2015        Current Status: Agreement signed        Achieved on Date: 14-08-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/71/RD/067        Contractor Name: Gaurav Builder       
Start Date: 21-08-2015        Intended Completion Date: 31-05-2017        Original End Date:  20-11-2016
Total Bond Cost: 32064880.58 (320.65 lakhs)        Variation Cost: -1255738.16 (-12.56 lakhs)     Hence Total Bond Cost is   30809142.42 (308.09 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 1811616 for 113 days        LD Analysis for Milestone2: calculated LD is Rs 4488960 for 280 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence1.76 KM27.461.76 KM1.76 KM8.9127.46
2.R/Wall, B/ Wall Type Protection works605.00 m68.78605.00 m605.00 m22.3368.78
3.G-30.63 KM6.820.63 KM0.63 KM2.216.82
4.PC/CC i/c Prime Coat, Tack Coat0.00 KM0.000.00 KM0.00 KM00.00
5.BM i/c Prime Coat, Tack Coat1.36 KM27.541.36 KM1.36 KM8.9427.54
6.SDBC i/c Tackcoat4.68 KM69.854.68 KM4.68 KM22.6769.85
7.Cause Way10.00 No29.7610.00 No10.00 No9.6629.76
8.Culverts/Scupper 9.00 No24.069.00 No9.00 No7.8124.06
9.longitudinal Drain3628.00 m10.583628.00 m3628.00 m3.4310.58
10.Crash Barrier500.00 m11.75500.00 m500.00 m3.8111.75
11.Parapet100.00 No2.17100.00 No100.00 No0.72.17
12.Road Furniture62.00 No1.4662.00 No62.00 No0.471.46
13.Other Allied Works & Finishing Work 1.00 Job27.851.00 Job1.00 Job9.0427.85
Total Amount: 308.08 100   308.08
Remarks: No Remarks       Work Program Made On: 07-05-2016       Updation of work program on: 14-08-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.12-January-201619.06  lakhs
2.29-February-201615.29  lakhs
3.28-March-20167.74  lakhs
4.16-May-201624.05  lakhs
5.14-July-201620.18  lakhs
6.31-December-201617.67  lakhs
7.25-February-201720.14  lakhs
8.03-March-201717.77  lakhs
9.30-June-201787.58  lakhs
10.16-October-201778.14  lakhs
Total 307.62  lakhs
% Payment 99.85 %
Advance Amount:  22.58  lakhs        Recovered Amount:  22.58  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 133     No. of Test Done : 146      No. of Test Passed : 133      No. of Test Failed : 13   Test report of this package
Number of Pics Available on Web Repository: 28
Number of Notice(s) issued: 108

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.31-05-2017Ch 3/11Sign boardAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
2.28-05-2017Ch 1/37SlipAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
3.27-05-2017Ch 2/31Instructiob has been followed, given by TL to make platform so water should not come on the road surfaceAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
4.27-05-2017Ch 2/31Instruction by TL to make a concrete platform so water did not come on the road surafaceAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
5.25-05-2017Ch 3/7Fixing sign boardAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
6.25-05-2017Ch 1/0Kilometer stone and delinatorAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
7.24-05-2017Ch 0/32Hectometer stone and delinatorAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
8.24-05-2017Ch 0/30Sign boardAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
9.24-05-2017Ch 0/0Board at starting pointAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
10.24-05-2017Ch 4/7Fixing of thermoplastic white strip on the edge of roadAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
11.10-04-20173/23Patch workDeepak GoelREDSC2 R&B WB Pauri See Pic
12.10-04-20173/23Patch workDeepak GoelREDSC2 R&B WB Pauri See Pic
13.10-04-2017Ch 3/17Rolling over bituminous layerAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
14.10-04-2017Ch 3/4Surface cleaning in progress for Bituminous layerAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
15.10-04-2017Ch 3/17Cleaning the surface for bituminous layerAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
16.09-04-2017Ch 0/10Plum concrete at the base of scupper in progressAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
17.09-04-2017Ch 2/12Parapet work in progressAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
18.08-04-2017Ch 3/4SlipAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
19.08-04-2017Ch 2/28M-10 Plum concreteAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
20.08-04-2017Ch 2/18Crash BarrierAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic